matching recommendationsSIC | 362 | Electrical Industrial Apparatus |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0545 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,420 | $15,470 | Implemented |
KU0545 # 03 Y:2000 | 03 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,890 | $20 | Implemented |
KU0545 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,580 | $1,150 | Implemented |
KU0545 # 05 Y:2000 | 05 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,510 | $1,770 | Implemented |
KU0545 # 06 Y:2000 | 06 | 2000 | COMBINE UTILITY METERS | $1,450 | $4,000 | Implemented |
KU0545 # 07 Y:2000 | 07 | 2000 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,020 | $0 | Implemented |
KU0545 # 08 Y:2000 | 08 | 2000 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $19,600 | $11,400 | Not Implemented |
KU0545 # 09 Y:2000 | 09 | 2000 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,530 | $3,000 | Not Implemented |
KU0545 # 01 Y:2000 | 01 | 2000 | OPTIMIZE PLANT POWER FACTOR | $12,740 | $4,370 | Implemented |
TN0692 # 01 Y:2000 | 01 | 2000 | RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION | $3,613,000 | $645,000 | Not Implemented |
TN0692 # 07 Y:2000 | 07 | 2000 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,600 | $900 | Implemented |
TN0692 # 09 Y:2000 | 09 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,115 | $1,300 | Implemented |
TN0692 # 06 Y:2000 | 06 | 2000 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,650 | $0 | Implemented |
TN0692 # 04 Y:2000 | 04 | 2000 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $7,220 | $11,900 | Not Implemented |
TN0692 # 08 Y:2000 | 08 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,336 | $0 | Implemented |
TN0692 # 02 Y:2000 | 02 | 2000 | ADD ADDITIONAL PRODUCTION SHIFT | $899,000 | $967,000 | Implemented |
TN0692 # 03 Y:2000 | 03 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,500 | $700 | Not Implemented |
TN0692 # 05 Y:2000 | 05 | 2000 | RECOVER AND REUSE WASTE MATERIAL | $4,210 | $0 | Implemented |
TN0682 # 07 Y:2000 | 07 | 2000 | COVER OPEN TANKS | $505 | $800 | Not Implemented |
TN0682 # 01 Y:2000 | 01 | 2000 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $37,600 | $7,800 | Implemented |
TN0682 # 02 Y:2000 | 02 | 2000 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $30,000 | $26,000 | Implemented |
TN0682 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,410 | $49,230 | Not Implemented |
TN0682 # 05 Y:2000 | 05 | 2000 | INSTALL SPECTRAL REFLECTORS / DELAMP | $6,460 | $3,340 | Not Implemented |
TN0682 # 06 Y:2000 | 06 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,650 | $215 | Not Implemented |
TN0682 # 04 Y:2000 | 04 | 2000 | COVER CONTAINERS TO MINIMIZE EVAPORATIVE LOSSES | $27,490 | $300 | Not Implemented |