Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
101
matching recommendationsSIC | 364 | Electric Lighting And Wiring Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NT0013 # 07 Y:2023 | 07 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $720,000 | $120,000 | Implemented |
NT0013 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,102 | $0 | Implemented |
NT0013 # 01 Y:2023 | 01 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $71,747 | $106,919 | Implemented |
NT0013 # 05 Y:2023 | 05 | 2023 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $17,430 | $54,000 | Implemented |
NT0013 # 04 Y:2023 | 04 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $49,000 | $83,421 | Implemented |
NT0013 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,755 | $21,512 | Implemented |
NT0013 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $10,076 | $5,043 | Not Implemented |
AM0821 # 06 Y:2021 | 06 | 2021 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $425 | $52 | Not Implemented |
AM0821 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,780 | $4,216 | Not Implemented |
AM0821 # 05 Y:2021 | 05 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,057 | $12 | Not Implemented |
AM0821 # 01 Y:2021 | 01 | 2021 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $17,688 | $5,000 | Not Implemented |
AM0821 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,460 | $1,000 | Not Implemented |
AM0821 # 02 Y:2021 | 02 | 2021 | PAY UTILITY BILLS ON TIME | $3,204 | $0 | Not Implemented |
AM0814 # 07 Y:2020 | 07 | 2020 | PAY UTILITY BILLS ON TIME | $490 | $0 | Implemented |
AM0814 # 06 Y:2020 | 06 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $500 | $25 | Implemented |
AM0814 # 05 Y:2020 | 05 | 2020 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,470 | $4,340 | Implemented |
AM0814 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,540 | $1,000 | Implemented |
AM0814 # 03 Y:2020 | 03 | 2020 | OPTIMIZE PLANT POWER FACTOR | $6,460 | $9,830 | Not Implemented |
AM0814 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,570 | $2,000 | Implemented |
AM0814 # 01 Y:2020 | 01 | 2020 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $74,300 | $7,400 | Implemented |
AM0814 # 08 Y:2020 | 08 | 2020 | USE SYNTHETIC LUBRICANT | $300 | $200 | Implemented |
AM0646 # 06 Y:2013 | 06 | 2013 | RELOCATE OVEN / FURNACE TO MORE EFFICIENT LOCATION | $2,505 | $5,010 | Not Implemented |
AM0646 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,610 | $2,250 | Implemented |
AM0646 # 07 Y:2013 | 07 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,850 | $500 | Implemented |
AM0646 # 08 Y:2013 | 08 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,470 | $770 | Implemented |