Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,242
matching recommendationsSIC | 364 | Electric Lighting And Wiring Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0661 # 05 Y:1999 | 05 | 1999 | FILTER AND REUSE HYDRAULIC OIL | $684 | $1,000 | Not Implemented |
GT0661 # 06 Y:1999 | 06 | 1999 | REDUCE SCRAP PRODUCTION | $215,560 | $112,500 | Implemented |
GT0661 # 07 Y:1999 | 07 | 1999 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $673,610 | $245,000 | Implemented |
GT0660 # 01 Y:1999 | 01 | 1999 | COMBINE UTILITY METERS | $2,900 | $0 | Not Implemented |
GT0660 # 02 Y:1999 | 02 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,800 | $10,000 | Not Implemented |
GT0660 # 03 Y:1999 | 03 | 1999 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $18,000 | $500 | Not Implemented |
GT0660 # 04 Y:1999 | 04 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,000 | $1,280 | Not Implemented |
GT0660 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,150 | $1,000 | Implemented |
GT0660 # 06 Y:1999 | 06 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $2,900 | $0 | Implemented |
GT0660 # 07 Y:1999 | 07 | 1999 | UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID | $416 | $1,000 | Not Implemented |
GT0660 # 08 Y:1999 | 08 | 1999 | MAINTAIN/ENLARGE A STOCK OF SPARE PARTS | $161,575 | $300,000 | Implemented |
OK0571 # 01 Y:1999 | 01 | 1999 | USE OPTIMUM THICKNESS INSULATION | $3,598 | $649 | Implemented |
OK0571 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $615 | $130 | Not Implemented |
OK0571 # 03 Y:1999 | 03 | 1999 | INSTALL OCCUPANCY SENSORS | $7,735 | $1,689 | Implemented |
OK0571 # 04 Y:1999 | 04 | 1999 | INSTALL SET-BACK TIMERS | $372 | $387 | Not Implemented |
OK0571 # 05 Y:1999 | 05 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $782 | $0 | Implemented |
OK0571 # 06 Y:1999 | 06 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $5,160 | $10,828 | Implemented |
OK0571 # 07 Y:1999 | 07 | 1999 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,160 | $0 | Not Implemented |
MA0423 # 01 Y:1998 | 01 | 1998 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,806 | $300 | Implemented |
MA0423 # 02 Y:1998 | 02 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $4,841 | $2,700 | Implemented |
MA0423 # 03 Y:1998 | 03 | 1998 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,343 | $234 | Implemented |
MA0423 # 04 Y:1998 | 04 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,279 | $80,000 | Not Implemented |
MA0423 # 05 Y:1998 | 05 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $585 | $2,627 | Implemented |
MA0423 # 06 Y:1998 | 06 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $187 | $294 | Not Implemented |
MA0423 # 07 Y:1998 | 07 | 1998 | INSTALL OCCUPANCY SENSORS | $149 | $257 | Not Implemented |