Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,242
matching recommendationsSIC | 364 | Electric Lighting And Wiring Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0153 # 01 Y:1998 | 01 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $541 | $800 | Not Implemented |
NC0153 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,691 | $18,850 | Not Implemented |
NC0153 # 03 Y:1998 | 03 | 1998 | ADD AREA LIGHTING SWITCHES | $91 | $300 | Not Implemented |
NC0153 # 04 Y:1998 | 04 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,508 | $500 | Not Implemented |
NC0153 # 05 Y:1998 | 05 | 1998 | INSTALL SKYLIGHTS | $10,344 | $36,000 | Not Implemented |
NC0153 # 06 Y:1998 | 06 | 1998 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $3,423 | $3,000 | Not Implemented |
NC0153 # 07 Y:1998 | 07 | 1998 | CLEAR AND RENT EXISTING SPACE | $28,000 | $20,500 | Not Implemented |
SD0210 # 01 Y:1998 | 01 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $901 | $0 | Not Implemented |
SD0210 # 02 Y:1998 | 02 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,500 | $36,250 | Not Implemented |
SD0210 # 03 Y:1998 | 03 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $8,860 | $3,100 | Not Implemented |
NC0152 # 01 Y:1998 | 01 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,388 | $1,000 | Not Implemented |
NC0152 # 02 Y:1998 | 02 | 1998 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $3,988 | $13,000 | Not Implemented |
NC0152 # 03 Y:1998 | 03 | 1998 | COVER OPEN TANKS | $1,006 | $100 | Implemented |
NC0152 # 04 Y:1998 | 04 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $396 | $80 | Not Implemented |
NC0152 # 05 Y:1998 | 05 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,160 | $0 | Implemented |
NC0152 # 06 Y:1998 | 06 | 1998 | REPROCESS SPENT OILS ON SITE FOR RE-USE | $3,010 | $5,000 | Not Implemented |
NC0152 # 07 Y:1998 | 07 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $563 | $200 | Implemented |
NC0152 # 08 Y:1998 | 08 | 1998 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $16,777 | $4,000 | Not Implemented |
NC0152 # 09 Y:1998 | 09 | 1998 | EXPAND OPERATIONS INTO UNUSED SPACE | $31,250 | $12,850 | Not Implemented |
NV0103 # 01 Y:1998 | 01 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $179 | $137 | Implemented |
NV0103 # 02 Y:1998 | 02 | 1998 | USE PHOTOCELL CONTROLS | $550 | $200 | Implemented |
NV0103 # 03 Y:1998 | 03 | 1998 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $912 | $750 | Implemented |
NV0103 # 04 Y:1998 | 04 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $44,986 | $9,960 | Implemented |
NV0103 # 05 Y:1998 | 05 | 1998 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $22,940 | $7,800 | Implemented |
NV0103 # 06 Y:1998 | 06 | 1998 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $33 | $0 | Not Implemented |