Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,242
matching recommendationsSIC | 364 | Electric Lighting And Wiring Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0330 # 05 Y:1990 | 05 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $607 | $444 | Not Implemented |
OK0325 # 01 Y:1990 | 01 | 1990 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,545 | $0 | Implemented |
OK0325 # 02 Y:1990 | 02 | 1990 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $570 | $0 | Implemented |
OK0325 # 03 Y:1990 | 03 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $652 | $3,027 | Not Implemented |
OK0325 # 04 Y:1990 | 04 | 1990 | RECOVER WASTE HEAT FROM EQUIPMENT | $333 | $1,280 | Not Implemented |
OK0325 # 05 Y:1990 | 05 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $165 | $0 | Implemented |
KU0324 # 01 Y:1990 | 01 | 1990 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $1,876 | $410 | Not Implemented |
KU0324 # 02 Y:1990 | 02 | 1990 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $1,759 | $4,000 | Implemented |
KU0324 # 03 Y:1990 | 03 | 1990 | INSTALL SET-BACK TIMERS | $821 | $600 | Not Implemented |
KU0324 # 04 Y:1990 | 04 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $544 | $0 | Implemented |
KU0324 # 05 Y:1990 | 05 | 1990 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $139 | $0 | Not Implemented |
RU0091 # 01 Y:1990 | 01 | 1990 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $457 | $0 | Implemented |
RU0091 # 02 Y:1990 | 02 | 1990 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $585 | $87 | Implemented |
RU0091 # 03 Y:1990 | 03 | 1990 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $424 | $200 | Implemented |
RU0091 # 04 Y:1990 | 04 | 1990 | IMPROVE LUBRICATION PRACTICES | $327 | $800 | Implemented |
RU0091 # 05 Y:1990 | 05 | 1990 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $367 | $2,297 | Implemented |
RU0091 # 06 Y:1990 | 06 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,072 | $406 | Implemented |
RU0091 # 07 Y:1990 | 07 | 1990 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,010 | $5,040 | Implemented |
RU0091 # 08 Y:1990 | 08 | 1990 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,092 | $500 | Implemented |
RU0091 # 09 Y:1990 | 09 | 1990 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $347 | $239 | Implemented |
RU0091 # 10 Y:1990 | 10 | 1990 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $946 | $402 | Implemented |
AM0089 # 01 Y:1990 | 01 | 1990 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $1,920 | $4,700 | Not Implemented |
AM0089 # 02 Y:1990 | 02 | 1990 | INSTALL SET-BACK TIMERS | $1,130 | $0 | Implemented |
AM0089 # 03 Y:1990 | 03 | 1990 | IMPROVE LUBRICATION PRACTICES | $561 | $0 | Implemented |
AM0089 # 04 Y:1990 | 04 | 1990 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $524 | $1,092 | Not Implemented |