Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
170
matching recommendationsSIC | 367 | Electronic Components And Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0508 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,041 | $8,081 | Implemented |
UD0508 # 08 Y:1996 | 08 | 1996 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $135,600 | $222,868 | Implemented |
UD0508 # 06 Y:1996 | 06 | 1996 | ELIMINATE/REDUCE AN OPERATION | $8,523 | $0 | Implemented |
UD0508 # 09 Y:1996 | 09 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,158 | $2,286 | Implemented |
UD0508 # 04 Y:1996 | 04 | 1996 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $31,719 | $11,000 | Implemented |
UD0508 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,088 | $2,314 | Implemented |
UD0508 # 10 Y:1996 | 10 | 1996 | RECOVER AND REUSE COOLING WATER | $5,108 | $5,000 | Implemented |
UD0508 # 07 Y:1996 | 07 | 1996 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $101,584 | $40,000 | Implemented |
UD0508 # 05 Y:1996 | 05 | 1996 | ELIMINATE/REDUCE AN OPERATION | $9,650 | $5,000 | Not Implemented |
UD0508 # 01 Y:1996 | 01 | 1996 | OPTIMIZE PLANT POWER FACTOR | $7,200 | $60,000 | Implemented |
WI0285 # 01 Y:1996 | 01 | 1996 | REDUCE VENTILATION AIR | $210,013 | $64,100 | Not Implemented |
WI0285 # 02 Y:1996 | 02 | 1996 | INCREASE USE OF AUTOMATION | $60,000 | $140,000 | Not Implemented |
WI0285 # 03 Y:1996 | 03 | 1996 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $2,786 | $0 | Implemented |
WI0285 # 04 Y:1996 | 04 | 1996 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,042 | $3,100 | Not Implemented |
WI0285 # 05 Y:1996 | 05 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,605 | $8,500 | Not Implemented |
WI0285 # 06 Y:1996 | 06 | 1996 | REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF | $2,549 | $10,500 | Not Implemented |
WI0285 # 07 Y:1996 | 07 | 1996 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,680 | $1,216 | Not Implemented |
WI0285 # 08 Y:1996 | 08 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,347 | $2,521 | Not Implemented |
WI0285 # 09 Y:1996 | 09 | 1996 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,100 | $0 | Not Implemented |
WI0285 # 10 Y:1996 | 10 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $380 | $500 | Not Implemented |
MA0369 # 03 Y:1996 | 03 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $4,903 | $8,750 | Not Implemented |
MA0369 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,735 | $49,531 | Not Implemented |
MA0369 # 05 Y:1996 | 05 | 1996 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,541 | $3,401 | Not Implemented |
MA0369 # 01 Y:1996 | 01 | 1996 | ADOPT IN-HOUSE MATERIAL GENERATION | $21,886 | $11,000 | Implemented |
MA0369 # 06 Y:1996 | 06 | 1996 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $919 | $0 | Implemented |