Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
150
matching recommendationsSIC | 367 | Electronic Components And Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2416 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,767 | $1,553 | n/a |
UC2416 # 10 Y:2024 | 10 | 2024 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $55,311 | $819,496 | n/a |
UC2416 # 09 Y:2024 | 09 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $80,097 | $301,647 | n/a |
UC2416 # 08 Y:2024 | 08 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $240,811 | $2,527,500 | n/a |
UC2416 # 07 Y:2024 | 07 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $294 | $139 | n/a |
UC2416 # 06 Y:2024 | 06 | 2024 | INSULATE BARE EQUIPMENT | $3,536 | $1,750 | n/a |
UC2416 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $73,494 | $29,062 | n/a |
UC2416 # 02 Y:2024 | 02 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $159,604 | $5,236 | n/a |
UC2416 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,662 | $1,600 | n/a |
UC2416 # 04 Y:2024 | 04 | 2024 | INSTALL OCCUPANCY SENSORS | $510 | $218 | n/a |
SU0562 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $656 | $0 | n/a |
SU0562 # 12 Y:2024 | 12 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $36,470 | $266,289 | n/a |
SU0562 # 11 Y:2024 | 11 | 2024 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $437 | $2,900 | n/a |
SU0562 # 10 Y:2024 | 10 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $291 | $1,234 | n/a |
SU0562 # 09 Y:2024 | 09 | 2024 | INSULATE BARE EQUIPMENT | $639 | $2,272 | n/a |
SU0562 # 08 Y:2024 | 08 | 2024 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $25,000 | $80,000 | n/a |
SU0562 # 07 Y:2024 | 07 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $419 | $632 | n/a |
SU0562 # 06 Y:2024 | 06 | 2024 | INSTALL BACK-UP EQUIPMENT | $75,000 | $86,000 | n/a |
SU0562 # 05 Y:2024 | 05 | 2024 | RECOVER WASTE HEAT FROM EQUIPMENT | $374 | $418 | n/a |
SU0562 # 04 Y:2024 | 04 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $3,064 | $120 | n/a |
SU0562 # 02 Y:2024 | 02 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,090 | $0 | n/a |
SU0562 # 01 Y:2024 | 01 | 2024 | DISCONNECT BALLASTS | $526 | $0 | n/a |
MI0451 # 03 Y:2024 | 03 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $8,251 | $10,833 | n/a |
MI0451 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,582 | $40 | n/a |
MI0451 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,862 | $16,333 | n/a |