Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
24
matching recommendationsSIC | 3674 | Semiconductors And Related Devices |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0793 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,117 | $0 | n/a |
OR0793 # 02 Y:2024 | 02 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,695 | $522 | n/a |
OR0793 # 01 Y:2024 | 01 | 2024 | ADOPT IN-HOUSE MATERIAL GENERATION | $13,689 | $209,197 | n/a |
OR0769 # 03 Y:2023 | 03 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,114 | $0 | Not Implemented |
OR0769 # 02 Y:2023 | 02 | 2023 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $9,780 | $12,978 | Not Implemented |
OR0769 # 01 Y:2023 | 01 | 2023 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $3,018 | $7,000 | Not Implemented |
OR0741 # 03 Y:2021 | 03 | 2021 | USE HEAT PUMP FOR SPACE CONDITIONING | $25,522 | $19,860 | Not Implemented |
OR0741 # 02 Y:2021 | 02 | 2021 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $56,371 | $0 | Not Implemented |
OR0741 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,176 | $40,448 | Not Implemented |
OR0726 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,581 | $7,570 | Implemented |
OR0726 # 03 Y:2019 | 03 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,031 | $3,570 | Not Implemented |
OR0726 # 02 Y:2019 | 02 | 2019 | REDUCE VENTILATION AIR | $1,259 | $0 | Implemented |
OR0335 # 04 Y:1998 | 04 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $310 | $0 | Implemented |
OR0335 # 03 Y:1998 | 03 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,260 | $0 | Not Implemented |
OR0335 # 02 Y:1998 | 02 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,045 | $1,000 | Implemented |
OR0335 # 01 Y:1998 | 01 | 1998 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $347,930 | $644,800 | Not Implemented |
OR0006 # 01 Y:1987 | 01 | 1987 | INSTALL SET-BACK TIMERS | $451 | $0 | Not Implemented |
OR0006 # 08 Y:1987 | 08 | 1987 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $6,089 | $13,772 | Not Implemented |
OR0006 # 07 Y:1987 | 07 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $874 | $1,320 | Implemented |
OR0006 # 06 Y:1987 | 06 | 1987 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $1,143 | $600 | Implemented |
OR0006 # 05 Y:1987 | 05 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $718 | $200 | Implemented |
OR0006 # 04 Y:1987 | 04 | 1987 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $25,130 | $7,000 | Not Implemented |
OR0006 # 03 Y:1987 | 03 | 1987 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $8,718 | $1,000 | Implemented |
OR0006 # 02 Y:1987 | 02 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,009 | $8,000 | Implemented |