Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsSIC | 3675 | Electronic Capacitors |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0219 # 12 Y:2005 | 12 | 2005 | ADD AREA LIGHTING SWITCHES | $4,267 | $10,645 | Implemented |
SU0219 # 07 Y:2005 | 07 | 2005 | DISCONNECT BALLASTS | $6,107 | $5,363 | Implemented |
LM0096 # 02 Y:2005 | 02 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $5,434 | $350 | Implemented |
LM0096 # 04 Y:2005 | 04 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $364 | $400 | Implemented |
LM0096 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,099 | $1,300 | Implemented |
LM0096 # 06 Y:2005 | 06 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,034 | $90 | Implemented |
UF0358 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,300 | $475 | Implemented |
UF0358 # 03 Y:2005 | 03 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,147 | $0 | Implemented |
UF0358 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,181 | $10,652 | Implemented |
UF0358 # 04 Y:2005 | 04 | 2005 | USE COMPRESSOR AIR FILTERS | $2,203 | $630 | Implemented |
UF0358 # 07 Y:2005 | 07 | 2005 | REDUCE HEAT GAIN BY WINDOW TINTING | $1,109 | $2,268 | Implemented |
UF0358 # 11 Y:2005 | 11 | 2005 | PAY UTILITY BILLS ON TIME | $856 | $0 | Implemented |
UF0358 # 09 Y:2005 | 09 | 2005 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $4,719 | $8,000 | Implemented |
WI0443 # 05 Y:2003 | 05 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $421 | $640 | Implemented |
WI0443 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $3,583 | $9,000 | Implemented |
WI0443 # 03 Y:2003 | 03 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,215 | $500 | Implemented |
WI0443 # 06 Y:2003 | 06 | 2003 | INSTALL OCCUPANCY SENSORS | $341 | $75 | Implemented |
WI0443 # 02 Y:2003 | 02 | 2003 | REDUCE EXCESSIVE BOILER BLOWDOWN | $1,964 | $4,500 | Implemented |
ME0224 # 01 Y:1997 | 01 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $47,583 | $18,145 | Implemented |
ME0224 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,674 | $5,557 | Implemented |
ME0224 # 05 Y:1997 | 05 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,067 | $279 | Implemented |
ME0224 # 06 Y:1997 | 06 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $965 | $250 | Implemented |
ME0224 # 07 Y:1997 | 07 | 1997 | INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT | $3,640 | $5,000 | Implemented |
ME0224 # 08 Y:1997 | 08 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $2,760 | $0 | Implemented |
ME0224 # 09 Y:1997 | 09 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $214 | $1,850 | Implemented |