Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
39
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0723 # 01 Y:2014 | 01 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $23,304 | $90,000 | Implemented |
MA0723 # 02 Y:2014 | 02 | 2014 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $20,745 | $110,500 | Implemented |
MA0723 # 03 Y:2014 | 03 | 2014 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $16,628 | $5,000 | Implemented |
MA0723 # 05 Y:2014 | 05 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,158 | $1,250 | Implemented |
MA0563 # 02 Y:2004 | 02 | 2004 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,769 | $650 | Implemented |
MA0563 # 04 Y:2004 | 04 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $116 | $0 | Implemented |
MA0563 # 01 Y:2004 | 01 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $39,550 | $12,000 | Implemented |
ME0238 # 10 Y:1998 | 10 | 1998 | UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID | $1,637 | $0 | Implemented |
ME0238 # 07 Y:1998 | 07 | 1998 | PAY UTILITY BILLS ON TIME | $176 | $0 | Implemented |
ME0238 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,607 | $17,669 | Implemented |
ME0238 # 05 Y:1998 | 05 | 1998 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $747 | $2,209 | Implemented |
ME0238 # 08 Y:1998 | 08 | 1998 | PAY UTILITY BILLS ON TIME | $87 | $0 | Implemented |
ME0227 # 06 Y:1997 | 06 | 1997 | USE OPTIMUM THICKNESS INSULATION | $408 | $75 | Implemented |
ME0227 # 07 Y:1997 | 07 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $359 | $100 | Implemented |
ME0227 # 04 Y:1997 | 04 | 1997 | USE OPTIMUM THICKNESS INSULATION | $515 | $588 | Implemented |
ME0227 # 10 Y:1997 | 10 | 1997 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $540 | $1,188 | Implemented |
ME0227 # 01 Y:1997 | 01 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,383 | $7,504 | Implemented |
ME0227 # 02 Y:1997 | 02 | 1997 | USE OPTIMUM THICKNESS INSULATION | $790 | $960 | Implemented |
ME0227 # 08 Y:1997 | 08 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $217 | $185 | Implemented |
ME0227 # 03 Y:1997 | 03 | 1997 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $756 | $0 | Implemented |
ME0226 # 01 Y:1997 | 01 | 1997 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $8,851 | $0 | Implemented |
ME0226 # 02 Y:1997 | 02 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,178 | $1,300 | Implemented |
ME0226 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,140 | $11,689 | Implemented |
ME0226 # 04 Y:1997 | 04 | 1997 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,451 | $1,500 | Implemented |
ME0226 # 10 Y:1997 | 10 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $1,892 | $12,000 | Implemented |