Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
496
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0282 # 05 Y:2001 | 05 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,312 | $2,000 | Not Implemented |
SD0282 # 06 Y:2001 | 06 | 2001 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $33,122 | $55,000 | Not Implemented |
SD0282 # 07 Y:2001 | 07 | 2001 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $55,555 | $10,000 | Implemented |
SD0282 # 08 Y:2001 | 08 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $83,687 | $110,000 | Not Implemented |
SD0282 # 09 Y:2001 | 09 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,108 | $8,000 | Not Implemented |
SD0282 # 10 Y:2001 | 10 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $348,473 | $150,000 | Not Implemented |
SD0282 # 11 Y:2001 | 11 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,832,890 | $1,400,000 | Not Implemented |
SD0282 # 12 Y:2001 | 12 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $5,600 | $500 | Not Implemented |
SD0282 # 13 Y:2001 | 13 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $21,020 | $20,000 | Not Implemented |
SD0282 # 14 Y:2001 | 14 | 2001 | USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME | $2,925 | $1,500 | Not Implemented |
SD0282 # 15 Y:2001 | 15 | 2001 | USE EVAPORATION TO CONCENTRATE MATERIAL | $13,681 | $3,000 | Not Implemented |
SD0282 # 16 Y:2001 | 16 | 2001 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $3,022,214 | $480,000 | Not Implemented |
SD0282 # 17 Y:2001 | 17 | 2001 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,777 | $0 | Implemented |
LM0007 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,501 | $630 | Implemented |
LM0007 # 02 Y:2001 | 02 | 2001 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $2,859 | $500 | Not Implemented |
LM0007 # 03 Y:2001 | 03 | 2001 | INSTALL SKYLIGHTS | $1,567 | $3,000 | Implemented |
LM0007 # 04 Y:2001 | 04 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,741 | $12,000 | Not Implemented |
LM0007 # 05 Y:2001 | 05 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $26,071 | $150 | Implemented |
LM0007 # 06 Y:2001 | 06 | 2001 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $20,250 | $416 | Not Implemented |
LM0007 # 07 Y:2001 | 07 | 2001 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $29,913 | $29,612 | Implemented |
SD0265 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,388 | $500 | Implemented |
SD0265 # 02 Y:2001 | 02 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,625 | $13,000 | Not Implemented |
SD0265 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,234 | $460 | Implemented |
SD0265 # 04 Y:2001 | 04 | 2001 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,874 | $1,012 | Implemented |
SD0265 # 05 Y:2001 | 05 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $4,783 | $12,500 | Not Implemented |