Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

51

matching recommendations
Reset
SIC 37 Transportation Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0437 # 05 Y:2017 05 2017 INCREASE ELECTRICAL CONDUCTOR SIZE TO REDUCE DISTRIBUTION LOSSES $35,693 $50,000 Not Implemented
LE0437 # 03 Y:2017 03 2017 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN $37,770 $36,000 Not Implemented
LE0437 # 04 Y:2017 04 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,482 $14,000 Not Implemented
LE0437 # 07 Y:2017 07 2017 CONSIDER POWER LOSS AS WELL AS INITIAL LOADS AND LOAD GROWTH IN DOWN-SIZING TRANSFORMERS $86,210 $200,000 Not Implemented
LE0437 # 01 Y:2017 01 2017 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $12,220 $7,000 Not Implemented
LE0437 # 08 Y:2017 08 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $21,363 $60,000 Not Implemented
LE0437 # 06 Y:2017 06 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,862 $12,000 Not Implemented
LE0437 # 02 Y:2017 02 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $26,208 $20,000 Not Implemented
DL0166 # 02 Y:2016 02 2016 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $4,815 $27,020 Not Implemented
DL0166 # 01 Y:2016 01 2016 RECOVER WASTE HEAT FROM EQUIPMENT $1,095 $1,036 Implemented
DL0166 # 08 Y:2016 08 2016 INSTALL OCCUPANCY SENSORS $2,400 $3,900 Not Implemented
DL0166 # 07 Y:2016 07 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,810 $35,710 Not Implemented
DL0166 # 03 Y:2016 03 2016 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $3,496 $9,820 Not Implemented
DL0166 # 04 Y:2016 04 2016 USE RADIANT HEATER FOR SPOT HEATING $1,310 $2,990 Not Implemented
DL0166 # 05 Y:2016 05 2016 INTERLOCK HEATING AND AIR CONDITIONING SYSTEMS TO PREVENT SIMULTANEOUS OPERATION $18,930 $4,739 Not Implemented
DL0166 # 06 Y:2016 06 2016 ADD AREA LIGHTING SWITCHES $1,520 $910 Not Implemented
DL0166 # 09 Y:2016 09 2016 UPGRADE CONTROLS ON COMPRESSORS $1,467 $565 Not Implemented
LE0326 # 01 Y:2011 01 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,373 $21,660 Implemented
LE0326 # 10 Y:2011 10 2011 RECOVER WASTE HEAT FROM EQUIPMENT $1,381 $2,000 Not Implemented
LE0326 # 03 Y:2011 03 2011 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $9,313 $108 Implemented
LE0326 # 08 Y:2011 08 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,956 $25 Implemented
LE0326 # 02 Y:2011 02 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $10,236 $51,475 Implemented
LE0326 # 06 Y:2011 06 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,255 $1,000 Implemented
LE0326 # 04 Y:2011 04 2011 INSTALL TIMERS AND/OR THERMOSTATS $6,020 $95 Implemented
LE0326 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,890 $10,580 Implemented