IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

155

matching recommendations
Reset
SIC 371 Motor Vehicles And Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LM0007 # 05 Y:2001 05 2001 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $26,071 $150 Implemented
LM0007 # 06 Y:2001 06 2001 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES $20,250 $416 Not Implemented
LM0007 # 07 Y:2001 07 2001 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS $29,913 $29,612 Implemented
SF0199 # 01 Y:2000 01 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $584 $0 Implemented
SF0199 # 02 Y:2000 02 2000 MODERATE COOLING TOWER OUTLET TEMPERATURE $4,250 $850 Implemented
SF0199 # 03 Y:2000 03 2000 RECOVER MECHANICAL ENERGY $2,307 $345 Not Implemented
SF0199 # 04 Y:2000 04 2000 RECOVER MECHANICAL ENERGY $2,300 $345 Not Implemented
SF0199 # 05 Y:2000 05 2000 INSTALL OCCUPANCY SENSORS $1,079 $1,080 Implemented
SF0199 # 06 Y:2000 06 2000 INSTALL OCCUPANCY SENSORS $1,583 $2,000 Implemented
SF0199 # 07 Y:2000 07 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $12,739 $36,345 Implemented
SF0199 # 08 Y:2000 08 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,178 $13,460 Implemented
SF0198 # 01 Y:2000 01 2000 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $1,396 $4,740 Implemented
SF0198 # 02 Y:2000 02 2000 INSTALL OCCUPANCY SENSORS $307 $600 Implemented
SF0198 # 03 Y:2000 03 2000 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $215 $0 Implemented
SF0198 # 04 Y:2000 04 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $412 $1,992 Implemented
SF0198 # 05 Y:2000 05 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,299 $4,199 Implemented
SF0198 # 06 Y:2000 06 2000 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $1,800 $80 Implemented
SF0198 # 07 Y:2000 07 2000 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $24,608 $3,400 Implemented
SF0198 # 08 Y:2000 08 2000 CHANGE OPERATING CONDITIONS $773 $0 Implemented
SD0213 # 01 Y:1999 01 1999 INSTALL SPECTRAL REFLECTORS / DELAMP $2,397 $1,830 Implemented
SD0213 # 02 Y:1999 02 1999 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $9,603 $5,830 Implemented
SD0213 # 03 Y:1999 03 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,133 $0 Implemented
SD0213 # 04 Y:1999 04 1999 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,873 $500 Implemented
SD0213 # 05 Y:1999 05 1999 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,948 $8,500 Not Implemented
SD0213 # 06 Y:1999 06 1999 REDESIGN PROCESS $28,000 $20,000 Not Implemented