Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,374
matching recommendationsSIC | 371 | Motor Vehicles And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0914 # 09 Y:2014 | 09 | 2014 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $3,388 | $0 | Not Implemented |
UD0914 # 10 Y:2014 | 10 | 2014 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $22,626 | $0 | Not Implemented |
UD0912 # 01 Y:2014 | 01 | 2014 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $10,884 | $0 | Not Implemented |
UD0912 # 02 Y:2014 | 02 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $724 | $1,400 | Not Implemented |
UD0912 # 03 Y:2014 | 03 | 2014 | INSULATE BARE EQUIPMENT | $5,893 | $1,130 | Not Implemented |
UD0912 # 04 Y:2014 | 04 | 2014 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $35,294 | $20,000 | Not Implemented |
UD0912 # 05 Y:2014 | 05 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $867 | $1,000 | Not Implemented |
UD0912 # 06 Y:2014 | 06 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,884 | $11,400 | Not Implemented |
UD0912 # 07 Y:2014 | 07 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,602 | $0 | Not Implemented |
UD0912 # 08 Y:2014 | 08 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,794 | $8,675 | Not Implemented |
UD0912 # 09 Y:2014 | 09 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,329 | $10,250 | Not Implemented |
UD0912 # 10 Y:2014 | 10 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,833 | $5,300 | Not Implemented |
UD0912 # 11 Y:2014 | 11 | 2014 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $47,606 | $0 | Not Implemented |
UD0912 # 12 Y:2014 | 12 | 2014 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $35,785 | $199,800 | Not Implemented |
NC0527 # 01 Y:2014 | 01 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $101,147 | $140,860 | Implemented |
NC0527 # 02 Y:2014 | 02 | 2014 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $23,485 | $5,000 | Implemented |
NC0527 # 03 Y:2014 | 03 | 2014 | REPLACE BOILER | $32,235 | $90,000 | Not Implemented |
NC0527 # 04 Y:2014 | 04 | 2014 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,800 | $33,000 | Not Implemented |
NC0527 # 05 Y:2014 | 05 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,403 | $100 | Implemented |
NC0527 # 06 Y:2014 | 06 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,883 | $10,000 | Not Implemented |
NC0527 # 07 Y:2014 | 07 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $13,647 | $10,000 | Implemented |
NC0527 # 08 Y:2014 | 08 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,785 | $300 | Not Implemented |
NC0527 # 09 Y:2014 | 09 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,636 | $1,503 | Implemented |
NC0527 # 10 Y:2014 | 10 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $945 | $432 | Not Implemented |
NC0527 # 11 Y:2014 | 11 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $1,768 | $4,256 | Implemented |