IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

519

matching recommendations
Reset
SIC 3713 Truck And Bus Bodies
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CC0029 # 03 Y:2023 03 2023 MAINTAIN MACHINES TO REDUCE LEAKS $11,616 $5,629 n/a
CC0029 # 07 Y:2023 07 2023 RECOVER WASTE HEAT FROM EQUIPMENT $38,352 $125,706 n/a
CC0029 # 01 Y:2023 01 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $30,487 $10,000 n/a
CC0029 # 04 Y:2023 04 2023 MINIMIZE CONDENSER COOLING WATER TEMPERATURE $12,405 $5,000 n/a
CC0029 # 02 Y:2023 02 2023 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $29,619 $32,820 n/a
CC0029 # 05 Y:2023 05 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $74,488 $34,000 n/a
CC0029 # 06 Y:2023 06 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $129,919 $1,308,548 n/a
AS0564 # 04 Y:2023 04 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,251 $143 Implemented
AS0564 # 01 Y:2023 01 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $30,388 $182,064 Not Implemented
AS0564 # 05 Y:2023 05 2023 INSTALL OCCUPANCY SENSORS $945 $110 Not Implemented
AS0564 # 03 Y:2023 03 2023 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $2,752 $63 Implemented
AS0564 # 02 Y:2023 02 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,294 $1,654 Implemented
AS0564 # 06 Y:2023 06 2023 INSTALL HEAT PIPES / RAISE COOLING SETPOINT $463 $71 Not Implemented
AS0564 # 07 Y:2023 07 2023 ELIMINATE LEAKS IN WATER LINES AND VALVES $29 $79 Implemented
GT0968 # 04 Y:2023 04 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $3,052 $3,250 Implemented
GT0968 # 03 Y:2023 03 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $73,640 $23,680 Implemented
GT0968 # 02 Y:2023 02 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $104,725 $13,000 Implemented
GT0968 # 05 Y:2023 05 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $159,818 $4,611,930 Not Implemented
GT0968 # 01 Y:2023 01 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $64,657 $1,850 Implemented
TT0293 # 05 Y:2023 05 2023 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING $3,025 $10,040 Not Implemented
TT0293 # 04 Y:2023 04 2023 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,615 $31,320 Implemented
TT0293 # 06 Y:2023 06 2023 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,199 $0 Implemented
TT0293 # 03 Y:2023 03 2023 UPGRADE CONTROLS ON COMPRESSORS $7,910 $600 Implemented
TT0293 # 02 Y:2023 02 2023 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $10,120 $0 Implemented
TT0293 # 01 Y:2023 01 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $20,707 $1,500 Implemented