IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

187

matching recommendations
Reset
SIC 3714 Motor Vehicle Parts And Accessories
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0408 # 05 Y:2012 05 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $154 $20 Implemented
BD0408 # 04 Y:2012 04 2012 RECOVER WASTE HEAT FROM EQUIPMENT $1,622 $4,000 Implemented
BD0408 # 03 Y:2012 03 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,611 $50 Not Implemented
BD0408 # 06 Y:2012 06 2012 RECOVER AND REUSE WASTE MATERIAL $975 $400 Implemented
BD0392 # 05 Y:2011 05 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $1,781 $3,500 Implemented
BD0392 # 06 Y:2011 06 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,411 $1,001 Not Implemented
BD0392 # 12 Y:2011 12 2011 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $12,800 $1,600 Implemented
BD0392 # 11 Y:2011 11 2011 RESCHEDULE BREAKS TO ALLOW FOR CONTINUOUS PRODUCTION $67,284 $10 Not Implemented
BD0392 # 10 Y:2011 10 2011 MINIMIZE WATER USAGE $1,525 $1,800 Not Implemented
BD0392 # 09 Y:2011 09 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $241 $250 Not Implemented
BD0392 # 08 Y:2011 08 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $419 $10 Implemented
BD0392 # 07 Y:2011 07 2011 INSTALL OCCUPANCY SENSORS $1,030 $1,000 Not Implemented
BD0392 # 04 Y:2011 04 2011 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,087 $7,610 Not Implemented
BD0392 # 03 Y:2011 03 2011 INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS $6,856 $55,000 Implemented
BD0392 # 02 Y:2011 02 2011 USE SOLAR HEAT TO MAKE ELECTRICTY $20,276 $73,000 Not Implemented
BD0392 # 01 Y:2011 01 2011 USE RADIANT HEATER FOR SPOT HEATING $9,888 $5,500 Not Implemented
IC0174 # 07 Y:2010 07 2010 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,895 $2,611 Not Implemented
IC0174 # 11 Y:2010 11 2010 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $1,966 $7,927 Not Implemented
IC0174 # 12 Y:2010 12 2010 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $257 $0 Not Implemented
IC0174 # 01 Y:2010 01 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,663 $0 Implemented
IC0174 # 02 Y:2010 02 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,638 $5,817 Not Implemented
IC0174 # 08 Y:2010 08 2010 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,429 $6,584 Not Implemented
IC0174 # 03 Y:2010 03 2010 INSTALL OCCUPANCY SENSORS $1,133 $2,415 Not Implemented
IC0174 # 04 Y:2010 04 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $287 $678 Not Implemented
IC0174 # 05 Y:2010 05 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $30,326 $4,485 Implemented