Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
125
matching recommendationsSIC | 372 | Aircraft And Parts |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CW0120 # 07 Y:2021 | 07 | 2021 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,000,000 | $122,000 | Implemented |
UD0998 # 09 Y:2019 | 09 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,344 | $2,520 | Not Implemented |
UD0998 # 08 Y:2019 | 08 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,135 | $5,000 | Not Implemented |
UD0998 # 07 Y:2019 | 07 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,380 | $1,315 | Not Implemented |
UD0998 # 06 Y:2019 | 06 | 2019 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $7,189 | $3,500 | Not Implemented |
UD0998 # 05 Y:2019 | 05 | 2019 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $965 | $280 | Not Implemented |
UD0998 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,128 | $0 | Not Implemented |
UD0998 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,093 | $0 | Not Implemented |
UD0998 # 03 Y:2019 | 03 | 2019 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $10,815 | $2,500 | Not Implemented |
UD0998 # 04 Y:2019 | 04 | 2019 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $1,888 | $40 | Not Implemented |
UD0939 # 02 Y:2016 | 02 | 2016 | COMBINE UTILITY METERS | $10,737 | $0 | Not Implemented |
UD0939 # 07 Y:2016 | 07 | 2016 | INSTALL OCCUPANCY SENSORS | $1,588 | $1,013 | Implemented |
UD0939 # 01 Y:2016 | 01 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,169 | $0 | Implemented |
UD0939 # 09 Y:2016 | 09 | 2016 | COVER OPEN TANKS | $1,526 | $740 | Not Implemented |
UD0939 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,740 | $1,000 | Implemented |
UD0939 # 10 Y:2016 | 10 | 2016 | COVER OPEN TANKS | $612 | $600 | Not Implemented |
UD0939 # 04 Y:2016 | 04 | 2016 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,358 | $400 | Not Implemented |
UD0939 # 11 Y:2016 | 11 | 2016 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $1,321 | $6,500 | Not Implemented |
UD0939 # 06 Y:2016 | 06 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $164 | $375 | Implemented |
UD0939 # 03 Y:2016 | 03 | 2016 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $369 | $700 | Not Implemented |
UD0939 # 08 Y:2016 | 08 | 2016 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,699 | $315 | Implemented |
WV0423 # 13 Y:2011 | 13 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $216 | $200 | Not Implemented |
WV0423 # 04 Y:2011 | 04 | 2011 | REPAIR AND ELIMINATE STEAM LEAKS | $1,472 | $626 | Implemented |
WV0423 # 03 Y:2011 | 03 | 2011 | DEVELOP A REPAIR/REPLACE POLICY | $1,913 | $1,429 | Not Implemented |
WV0423 # 02 Y:2011 | 02 | 2011 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $6,406 | $12,655 | Not Implemented |