IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

115

matching recommendations
Reset
SIC 372 Aircraft And Parts
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD1066 # 04 Y:2023 04 2023 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $671 $1,639 Implemented
UD1066 # 06 Y:2023 06 2023 PROVIDE PROPER MAINTENANCE OF MOTOR DRIVEN EQUIPMENT $21,383 $42,766 Not Implemented
UD1066 # 08 Y:2023 08 2023 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $5 $0 Not Implemented
UD1066 # 03 Y:2023 03 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,718 $952 Not Implemented
UD1066 # 02 Y:2023 02 2023 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $3,630 $1,415 Implemented
UD1066 # 01 Y:2023 01 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $5,952 $600 Implemented
UD1066 # 07 Y:2023 07 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $16,743 $18,195 Not Implemented
UD1066 # 05 Y:2023 05 2023 INSTALL OCCUPANCY SENSORS $1,566 $1,770 Not Implemented
CW0120 # 07 Y:2021 07 2021 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $1,000,000 $122,000 Implemented
CW0120 # 06 Y:2021 06 2021 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $899 $0 Implemented
CW0120 # 05 Y:2021 05 2021 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $1,965 $510 Implemented
CW0120 # 04 Y:2021 04 2021 MODIFY STARTUP/SHUTDOWN TIMES $2,380 $100,000 Implemented
CW0120 # 03 Y:2021 03 2021 USE BATTERY STORAGE FOR DEMAND CONTROL $18,089 $25,885 Implemented
CW0120 # 02 Y:2021 02 2021 INSTALL BACK-UP EQUIPMENT $32,054 $93,000 Implemented
CW0120 # 01 Y:2021 01 2021 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $30,000 $70,084 Implemented
CW0120 # 08 Y:2021 08 2021 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $217 $86 Implemented
UD0998 # 08 Y:2019 08 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,135 $5,000 Not Implemented
UD0998 # 09 Y:2019 09 2019 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,344 $2,520 Not Implemented
UD0998 # 07 Y:2019 07 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,380 $1,315 Not Implemented
UD0998 # 01 Y:2019 01 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,128 $0 Not Implemented
UD0998 # 06 Y:2019 06 2019 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $7,189 $3,500 Not Implemented
UD0998 # 05 Y:2019 05 2019 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $965 $280 Not Implemented
UD0998 # 04 Y:2019 04 2019 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $1,888 $40 Not Implemented
UD0998 # 03 Y:2019 03 2019 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $10,815 $2,500 Not Implemented
UD0998 # 02 Y:2019 02 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,093 $0 Not Implemented