Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
92
matching recommendationsSIC | 372 | Aircraft And Parts |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0371 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,368 | $650 | Implemented |
UF0371 # 01 Y:2005 | 01 | 2005 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $6,120 | $978 | Implemented |
UF0371 # 13 Y:2005 | 13 | 2005 | IMPROVE SPACE COMFORT CONDITIONING | $100,000 | $50,000 | Implemented |
UF0371 # 12 Y:2005 | 12 | 2005 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $100,000 | $25,000 | Implemented |
UF0371 # 11 Y:2005 | 11 | 2005 | IMPROVE SPACE COMFORT CONDITIONING | $1,596 | $26,800 | Implemented |
UF0371 # 10 Y:2005 | 10 | 2005 | REDESIGN PROCESS | $61,200 | $1,000,000 | Not Implemented |
UF0371 # 09 Y:2005 | 09 | 2005 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $5,477 | $800 | Implemented |
UF0371 # 08 Y:2005 | 08 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,385 | $0 | Implemented |
UF0371 # 07 Y:2005 | 07 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $18,424 | $0 | Implemented |
UF0371 # 06 Y:2005 | 06 | 2005 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $7,254 | $20,000 | Not Implemented |
UF0371 # 05 Y:2005 | 05 | 2005 | INSTALL OCCUPANCY SENSORS | $2,952 | $4,688 | Not Implemented |
UF0371 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,453 | $675 | Implemented |
UF0371 # 03 Y:2005 | 03 | 2005 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $6,271 | $1,680 | Implemented |
AS0412 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $37,489 | $5,000 | Implemented |
AS0412 # 07 Y:2005 | 07 | 2005 | USE SOLAR HEAT TO HEAT WATER | $345 | $2,800 | Implemented |
AS0412 # 06 Y:2005 | 06 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $762 | $25 | Implemented |
AS0412 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,173 | $10,610 | Implemented |
AS0412 # 04 Y:2005 | 04 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $15,470 | $14,400 | Implemented |
AS0412 # 03 Y:2005 | 03 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $23,601 | $2,000 | Implemented |
AS0412 # 02 Y:2005 | 02 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $37,178 | $15,000 | Implemented |
TA0106 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,400 | $12,395 | Implemented |
TA0106 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,775 | $175 | Implemented |
TA0106 # 01 Y:2005 | 01 | 2005 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $28,674 | $-14,337 | Implemented |
TA0106 # 05 Y:2005 | 05 | 2005 | INSTALL OCCUPANCY SENSORS | $1,150 | $100 | Implemented |
TA0106 # 03 Y:2005 | 03 | 2005 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $4,400 | $185 | Not Implemented |