Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
144
matching recommendationsSIC | 3728 | Aircraft Parts And Equipment, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0389 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,739 | $33,655 | Implemented |
MI0389 # 04 Y:2021 | 04 | 2021 | INSTALL EFFICIENT RECTIFIERS | $21,196 | $55,920 | Implemented |
MI0389 # 05 Y:2021 | 05 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $19,025 | $120 | Implemented |
MI0389 # 06 Y:2021 | 06 | 2021 | INSULATE BARE EQUIPMENT | $15,421 | $6,812 | Not Implemented |
MI0389 # 07 Y:2021 | 07 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $10,000 | $480 | Not Implemented |
MI0389 # 08 Y:2021 | 08 | 2021 | USE COMPRESSOR AIR FILTERS | $1,420 | $1,100 | Implemented |
MI0389 # 09 Y:2021 | 09 | 2021 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $1,362 | $616 | Implemented |
MI0389 # 10 Y:2021 | 10 | 2021 | COMBINE UTILITY METERS | $776 | $240 | Not Implemented |
MI0384 # 01 Y:2020 | 01 | 2020 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $69,936 | $480 | Implemented |
MI0384 # 02 Y:2020 | 02 | 2020 | USE SOLAR HEAT TO HEAT WATER | $26,710 | $12,200 | Not Implemented |
MI0384 # 03 Y:2020 | 03 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $4,404 | $16,320 | Implemented |
MI0384 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,546 | $3,927 | Implemented |
MI0384 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,610 | $2,100 | Implemented |
MI0384 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,477 | $8,668 | Implemented |
MI0384 # 07 Y:2020 | 07 | 2020 | PAY UTILITY BILLS ON TIME | $1,659 | $0 | Implemented |
MI0384 # 08 Y:2020 | 08 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,572 | $1,980 | Implemented |
MI0367 # 01 Y:2020 | 01 | 2020 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $38,331 | $2,480 | Implemented |
MI0367 # 02 Y:2020 | 02 | 2020 | USE BATTERY STORAGE FOR DEMAND CONTROL | $21,335 | $38,237 | Not Implemented |
MI0367 # 03 Y:2020 | 03 | 2020 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $18,517 | $2,480 | Implemented |
MI0367 # 04 Y:2020 | 04 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,815 | $120 | Implemented |
MI0367 # 05 Y:2020 | 05 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,479 | $9,842 | Implemented |
MI0367 # 06 Y:2020 | 06 | 2020 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $3,241 | $4,900 | Not Implemented |
MI0367 # 07 Y:2020 | 07 | 2020 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $3,190 | $2,500 | Not Implemented |
MI0367 # 08 Y:2020 | 08 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,348 | $1,980 | Not Implemented |
MI0278 # 01 Y:2015 | 01 | 2015 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $103,740 | $220,000 | Not Implemented |