Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
127
matching recommendationsSIC | 38 | Instruments And Related Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0475 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $975 | $1,124 | Not Implemented |
NC0475 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,801 | $48,075 | Not Implemented |
NC0387 # 09 Y:2009 | 09 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $712 | $351 | Not Implemented |
NC0387 # 08 Y:2009 | 08 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,156 | $85,555 | Implemented |
NC0387 # 07 Y:2009 | 07 | 2009 | DEVELOP A REPAIR/REPLACE POLICY | $2,019 | $2,198 | Not Implemented |
NC0387 # 06 Y:2009 | 06 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,447 | $100 | Implemented |
NC0387 # 05 Y:2009 | 05 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,105 | $7,000 | Not Implemented |
NC0387 # 04 Y:2009 | 04 | 2009 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $21,000 | $25,000 | Not Implemented |
NC0387 # 03 Y:2009 | 03 | 2009 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $44,613 | $45,000 | Not Implemented |
NC0387 # 02 Y:2009 | 02 | 2009 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $51,343 | $72,000 | Not Implemented |
NC0387 # 01 Y:2009 | 01 | 2009 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $202,240 | $400,000 | Not Implemented |
NC0373 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,639 | $5,398 | Implemented |
NC0373 # 01 Y:2008 | 01 | 2008 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $4,343 | $15,000 | Not Implemented |
NC0373 # 04 Y:2008 | 04 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,993 | $16,000 | Not Implemented |
NC0373 # 03 Y:2008 | 03 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $650 | $100 | Implemented |
NC0373 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,879 | $9,158 | Implemented |
NC0373 # 02 Y:2008 | 02 | 2008 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $13,018 | $26,250 | Not Implemented |
NC0310 # 03 Y:2005 | 03 | 2005 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $60,000 | $20,500 | Implemented |
NC0310 # 02 Y:2005 | 02 | 2005 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $97,500 | $61,250 | Implemented |
NC0310 # 01 Y:2005 | 01 | 2005 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $167,500 | $150,000 | Implemented |
NC0310 # 04 Y:2005 | 04 | 2005 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $34,863 | $30,000 | Not Implemented |
NC0310 # 05 Y:2005 | 05 | 2005 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $1,451 | $3,000 | Implemented |
NC0310 # 06 Y:2005 | 06 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,830 | $875 | Implemented |
NC0310 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $339 | $616 | Not Implemented |
NC0310 # 08 Y:2005 | 08 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $509 | $100 | Implemented |