Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
37
matching recommendationsSIC | 382 | Measuring And Controlling Devices |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0307 # 02 Y:2004 | 02 | 2004 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $72,400 | $49,500 | Implemented |
NC0307 # 03 Y:2004 | 03 | 2004 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $32,361 | $24,000 | Not Implemented |
NC0307 # 04 Y:2004 | 04 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $16,989 | $31,278 | Not Implemented |
NC0307 # 05 Y:2004 | 05 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,342 | $1,456 | Not Implemented |
NC0307 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $313 | $381 | Not Implemented |
NC0307 # 07 Y:2004 | 07 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,171 | $100 | Implemented |
NC0307 # 01 Y:2004 | 01 | 2004 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $151,225 | $150,000 | Not Implemented |
SU0196 # 02 Y:2004 | 02 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,956 | $0 | Implemented |
SU0196 # 05 Y:2004 | 05 | 2004 | INSTALL OCCUPANCY SENSORS | $344 | $888 | Not Implemented |
SU0196 # 03 Y:2004 | 03 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $431 | $0 | Not Implemented |
SU0196 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,388 | $653 | Implemented |
SU0196 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $4,000 | $0 | Implemented |
OR0461 # 01 Y:2004 | 01 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $2,372,930 | $1,150 | Implemented |
OR0461 # 02 Y:2004 | 02 | 2004 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $303,000 | $1,000 | Not Implemented |
OR0461 # 03 Y:2004 | 03 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,290 | $2,690 | Implemented |
OR0461 # 04 Y:2004 | 04 | 2004 | INSTALL OCCUPANCY SENSORS | $1,910 | $875 | Not Implemented |
SD0341 # 04 Y:2004 | 04 | 2004 | INSTALL OCCUPANCY SENSORS | $965 | $400 | Implemented |
SD0341 # 05 Y:2004 | 05 | 2004 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $5,607 | $10,000 | Not Implemented |
SD0341 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,274 | $3,721 | Not Implemented |
SD0341 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $570 | $200 | Implemented |
SD0341 # 01 Y:2004 | 01 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $961 | $600 | Not Implemented |
CO0544 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,260 | $80,750 | Not Implemented |
CO0544 # 05 Y:2004 | 05 | 2004 | INSULATE BARE EQUIPMENT | $310 | $250 | Implemented |
CO0544 # 04 Y:2004 | 04 | 2004 | COVER OPEN TANKS | $2,630 | $2,150 | Not Implemented |
CO0544 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,600 | $300 | Implemented |