Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
77
matching recommendationsSIC | 3851 | Ophthalmic Goods |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0840 # 03 Y:2022 | 03 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,180 | $699 | Implemented |
MA0840 # 05 Y:2022 | 05 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,635 | $1,000 | Implemented |
WV0587 # 08 Y:2019 | 08 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,563 | $600 | Implemented |
WV0587 # 12 Y:2019 | 12 | 2019 | INSTALL OCCUPANCY SENSORS | $1,787 | $1,750 | Implemented |
WV0587 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,112 | $300 | Implemented |
WV0587 # 04 Y:2019 | 04 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,887 | $4,500 | Implemented |
WV0587 # 11 Y:2019 | 11 | 2019 | INSULATE BARE EQUIPMENT | $2,257 | $2,624 | Implemented |
WV0587 # 07 Y:2019 | 07 | 2019 | DEVELOP A REPAIR/REPLACE POLICY | $5,261 | $650 | Implemented |
MI0352 # 04 Y:2019 | 04 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $6,201 | $7,920 | Implemented |
MI0352 # 01 Y:2019 | 01 | 2019 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $15,430 | $10,964 | Implemented |
MI0352 # 02 Y:2019 | 02 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,207 | $3,600 | Implemented |
MI0352 # 06 Y:2019 | 06 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,012 | $100 | Implemented |
MI0352 # 03 Y:2019 | 03 | 2019 | USE SOLAR HEAT TO HEAT WATER | $7,116 | $10,125 | Implemented |
MI0352 # 05 Y:2019 | 05 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,725 | $2,284 | Implemented |
MI0352 # 10 Y:2019 | 10 | 2019 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $603 | $2,315 | Implemented |
MI0352 # 12 Y:2019 | 12 | 2019 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $518 | $2,294 | Implemented |
MI0352 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,851 | $1,846 | Implemented |
MI0352 # 09 Y:2019 | 09 | 2019 | INSTALL OCCUPANCY SENSORS | $656 | $319 | Implemented |
CO0710 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,710 | $340 | Implemented |
CO0710 # 03 Y:2015 | 03 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $470 | $60 | Implemented |
MI0230 # 12 Y:2012 | 12 | 2012 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $6,487 | $2,848 | Implemented |
MI0230 # 03 Y:2012 | 03 | 2012 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $88,716 | $46,097 | Implemented |
MI0230 # 10 Y:2012 | 10 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,962 | $1,589 | Implemented |
MI0230 # 05 Y:2012 | 05 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $45,101 | $41,600 | Implemented |
MI0230 # 15 Y:2012 | 15 | 2012 | INSTALL OCCUPANCY SENSORS | $2,794 | $320 | Implemented |