Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
78
matching recommendationsSIC | 3861 | Photographic Equipment And Supplies |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0668 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,597 | $0 | Implemented |
OK0668 # 05 Y:2003 | 05 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $67,238 | $0 | Implemented |
OK0668 # 06 Y:2003 | 06 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $21,821 | $1,125 | Implemented |
OK0668 # 09 Y:2003 | 09 | 2003 | INSULATE BARE EQUIPMENT | $1,369 | $1,455 | Implemented |
OK0668 # 13 Y:2003 | 13 | 2003 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $38,034 | $1,647 | Implemented |
UD0644 # 02 Y:2002 | 02 | 2002 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $18,360 | $0 | Implemented |
UD0644 # 06 Y:2002 | 06 | 2002 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,953 | $131 | Implemented |
UD0644 # 07 Y:2002 | 07 | 2002 | AIR CONDITION ONLY SPACE NECESSARY | $1,285 | $0 | Implemented |
UD0644 # 09 Y:2002 | 09 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $475 | $1,348 | Implemented |
TA0020 # 02 Y:2001 | 02 | 2001 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,751 | $0 | Implemented |
TA0020 # 03 Y:2001 | 03 | 2001 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $3,260 | $240 | Implemented |
TA0020 # 04 Y:2001 | 04 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,415 | $1,715 | Implemented |
TA0020 # 05 Y:2001 | 05 | 2001 | INSULATE BARE EQUIPMENT | $1,110 | $321 | Implemented |
TA0020 # 06 Y:2001 | 06 | 2001 | INSULATE BARE EQUIPMENT | $685 | $140 | Implemented |
TA0020 # 07 Y:2001 | 07 | 2001 | INSTALL OCCUPANCY SENSORS | $584 | $320 | Implemented |
TA0020 # 08 Y:2001 | 08 | 2001 | INSULATE BARE EQUIPMENT | $370 | $160 | Implemented |
DS0070 # 04 Y:1996 | 04 | 1996 | TURN OFF EQUIPMENT WHEN NOT IN USE | $181 | $0 | Implemented |
DS0070 # 05 Y:1996 | 05 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $1,684 | $2,310 | Implemented |
DS0058 # 04 Y:1996 | 04 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,728 | $300 | Implemented |
DS0058 # 06 Y:1996 | 06 | 1996 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,885 | $1,050 | Implemented |
DS0058 # 02 Y:1996 | 02 | 1996 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $638 | $175 | Implemented |
DS0058 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $859 | $859 | Implemented |
WI0148 # 01 Y:1992 | 01 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $2,857 | $400 | Implemented |
WI0148 # 07 Y:1992 | 07 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $134 | $640 | Implemented |
WI0148 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $110 | $2 | Implemented |