Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,162
matching recommendationsSIC | 39 | Miscellaneous Manufacturing Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0065 # 02 Y:2004 | 02 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,450 | $0 | Implemented |
UU0065 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,345 | $1,100 | Implemented |
UU0065 # 04 Y:2004 | 04 | 2004 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,188 | $225 | Implemented |
CO0535 # 02 Y:2003 | 02 | 2003 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $9,820 | $6,420 | Implemented |
CO0535 # 03 Y:2003 | 03 | 2003 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $7,160 | $15,760 | Implemented |
CO0535 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,340 | $750 | Implemented |
CO0535 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,250 | $9,690 | Implemented |
CO0535 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $411 | $112 | Implemented |
MS0234 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,578 | $99 | Implemented |
MS0234 # 03 Y:2003 | 03 | 2003 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $237 | $0 | Implemented |
MS0234 # 06 Y:2003 | 06 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $64 | $115 | Implemented |
LL0177 # 01 Y:2003 | 01 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,804 | $4,160 | Implemented |
LL0177 # 02 Y:2003 | 02 | 2003 | PAY UTILITY BILLS ON TIME | $2,710 | $30 | Implemented |
LL0177 # 03 Y:2003 | 03 | 2003 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,193 | $316 | Implemented |
LL0177 # 04 Y:2003 | 04 | 2003 | INSULATE BARE EQUIPMENT | $1,253 | $1,600 | Implemented |
LL0177 # 07 Y:2003 | 07 | 2003 | INSTALL OCCUPANCY SENSORS | $30 | $43 | Implemented |
WV0268 # 01 Y:2003 | 01 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,435 | $108 | Implemented |
WV0268 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,612 | $250 | Implemented |
WV0268 # 05 Y:2003 | 05 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,261 | $720 | Implemented |
WV0268 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,769 | $20,880 | Implemented |
WV0268 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,262 | $0 | Implemented |
WV0268 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,404 | $6,834 | Implemented |
WV0268 # 09 Y:2003 | 09 | 2003 | INSTALL OCCUPANCY SENSORS | $927 | $600 | Implemented |
WV0268 # 10 Y:2003 | 10 | 2003 | INSULATE BARE EQUIPMENT | $24,688 | $2,019 | Implemented |
WV0268 # 13 Y:2003 | 13 | 2003 | DEVELOP A REPAIR/REPLACE POLICY | $6,152 | $450 | Implemented |