Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
303
matching recommendationsSIC | 394 | Toys And Sporting Goods |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0490 # 10 Y:2005 | 10 | 2005 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $235 | $100 | Implemented |
AM0490 # 08 Y:2005 | 08 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $270 | $200 | Implemented |
AM0490 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $930 | $475 | Implemented |
IA0354 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $885 | $2,484 | Implemented |
IA0354 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $973 | $1,626 | Implemented |
IA0354 # 04 Y:2004 | 04 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $389 | $710 | Implemented |
IA0354 # 03 Y:2004 | 03 | 2004 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $561 | $238 | Implemented |
IA0354 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,722 | $207 | Implemented |
UU0065 # 04 Y:2004 | 04 | 2004 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,188 | $225 | Implemented |
UU0065 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,345 | $1,100 | Implemented |
UU0065 # 02 Y:2004 | 02 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,450 | $0 | Implemented |
LL0177 # 01 Y:2003 | 01 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,804 | $4,160 | Implemented |
LL0177 # 02 Y:2003 | 02 | 2003 | PAY UTILITY BILLS ON TIME | $2,710 | $30 | Implemented |
LL0177 # 03 Y:2003 | 03 | 2003 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,193 | $316 | Implemented |
LL0177 # 04 Y:2003 | 04 | 2003 | INSULATE BARE EQUIPMENT | $1,253 | $1,600 | Implemented |
LL0177 # 07 Y:2003 | 07 | 2003 | INSTALL OCCUPANCY SENSORS | $30 | $43 | Implemented |
BD0215 # 01 Y:2002 | 01 | 2002 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $20,511 | $4,000 | Implemented |
BD0215 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $562 | $400 | Implemented |
UU0022 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,373 | $365 | Implemented |
UU0022 # 06 Y:2002 | 06 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,022 | $326 | Implemented |
UU0022 # 07 Y:2002 | 07 | 2002 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $32,358 | $17,100 | Implemented |
UU0022 # 02 Y:2002 | 02 | 2002 | OPTIMIZE PLANT POWER FACTOR | $5,007 | $7,160 | Implemented |
UU0021 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,467 | $460 | Implemented |
UU0021 # 06 Y:2002 | 06 | 2002 | RECOVER AND REUSE WASTE MATERIAL | $62,291 | $17,100 | Implemented |
UU0021 # 02 Y:2002 | 02 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,462 | $610 | Implemented |