Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
137
matching recommendationsSIC | 3944 | Games, Toys, and Children's Vehicles, Except Dolls and Bicycles |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1021 # 10 Y:2020 | 10 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,902 | $7,800 | Not Implemented |
UD1021 # 03 Y:2020 | 03 | 2020 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $5,965 | $1,400 | Not Implemented |
UD1021 # 02 Y:2020 | 02 | 2020 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $32,724 | $0 | Implemented |
UD1021 # 01 Y:2020 | 01 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $10,283 | $0 | Implemented |
UD1021 # 08 Y:2020 | 08 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,419 | $37,053 | Implemented |
UD1021 # 07 Y:2020 | 07 | 2020 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $8,594 | $1,590 | Not Implemented |
UD1021 # 06 Y:2020 | 06 | 2020 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,902 | $2,000 | Implemented |
UD1021 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,841 | $0 | Implemented |
UD1021 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,342 | $0 | Implemented |
UD1021 # 11 Y:2020 | 11 | 2020 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $249 | $240 | Not Implemented |
UD1021 # 09 Y:2020 | 09 | 2020 | INSTALL OCCUPANCY SENSORS | $16,106 | $2,800 | Implemented |
MA0798 # 08 Y:2019 | 08 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $922 | $978 | Not Implemented |
MA0798 # 07 Y:2019 | 07 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,849 | $2,001 | Implemented |
MA0798 # 01 Y:2019 | 01 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $39,625 | $48,500 | Implemented |
MA0798 # 09 Y:2019 | 09 | 2019 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $512 | $200 | Implemented |
MA0798 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,904 | $2,765 | Not Implemented |
MA0798 # 06 Y:2019 | 06 | 2019 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $2,585 | $500 | Not Implemented |
MA0798 # 02 Y:2019 | 02 | 2019 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $18,484 | $80,000 | Implemented |
MA0798 # 03 Y:2019 | 03 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,569 | $8,930 | Not Implemented |
MA0798 # 05 Y:2019 | 05 | 2019 | INSULATE BARE EQUIPMENT | $3,333 | $1,801 | Implemented |
MZ0199 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $31,470 | $116,250 | Not Implemented |
MZ0199 # 01 Y:2015 | 01 | 2015 | CONDENSE OPERATION INTO ONE BUILDING | $14,201 | $28,800 | Not Implemented |
MZ0199 # 02 Y:2015 | 02 | 2015 | CONDENSE OPERATION INTO ONE BUILDING | $19,376 | $2,500 | Not Implemented |
MZ0199 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $1,508 | $440 | Not Implemented |
MZ0199 # 06 Y:2015 | 06 | 2015 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $4,502 | $27,000 | Not Implemented |