Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
556
matching recommendationsSIC | 4941 | Water Supply |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0914 # 05 Y:2018 | 05 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,028 | $800 | Not Implemented |
GT0914 # 06 Y:2018 | 06 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,676 | $26,357 | Implemented |
WV0558 # 01 Y:2018 | 01 | 2018 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $17,760 | $81,750 | Not Implemented |
WV0558 # 02 Y:2018 | 02 | 2018 | PROVIDE PROPER MAINTENANCE OF MOTOR DRIVEN EQUIPMENT | $10,332 | $20,570 | Not Implemented |
WV0558 # 03 Y:2018 | 03 | 2018 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,223 | $1,000 | Implemented |
WV0558 # 04 Y:2018 | 04 | 2018 | INSTALL OCCUPANCY SENSORS | $2,061 | $1,265 | Not Implemented |
WV0558 # 05 Y:2018 | 05 | 2018 | INTERLOCK HEATING AND AIR CONDITIONING SYSTEMS TO PREVENT SIMULTANEOUS OPERATION | $1,726 | $7,488 | Implemented |
WV0558 # 06 Y:2018 | 06 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $629 | $579 | Implemented |
WV0558 # 07 Y:2018 | 07 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $406 | $2,005 | Not Implemented |
WV0558 # 08 Y:2018 | 08 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $277 | $522 | Implemented |
LS0011 # 01 Y:2017 | 01 | 2017 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $30,575 | $67,000 | Not Implemented |
LS0011 # 02 Y:2017 | 02 | 2017 | INSTALL TIMERS AND/OR THERMOSTATS | $1,608 | $600 | Not Implemented |
LS0011 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,983 | $9,913 | Not Implemented |
LS0011 # 04 Y:2017 | 04 | 2017 | INSTALL OCCUPANCY SENSORS | $170 | $210 | Not Implemented |
LS0011 # 05 Y:2017 | 05 | 2017 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $291 | $0 | Implemented |
UU0123 # 01 Y:2017 | 01 | 2017 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $22,871 | $23,400 | Implemented |
UU0123 # 02 Y:2017 | 02 | 2017 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $7,624 | $13,970 | Implemented |
UU0123 # 03 Y:2017 | 03 | 2017 | METER WASTE WATER | $4,100 | $0 | Not Implemented |
UU0123 # 04 Y:2017 | 04 | 2017 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $3,374 | $5,770 | Implemented |
UU0123 # 05 Y:2017 | 05 | 2017 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $3,114 | $4,625 | Implemented |
UD0974 # 01 Y:2017 | 01 | 2017 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $31,690 | $0 | Not Implemented |
UD0974 # 02 Y:2017 | 02 | 2017 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $10,184 | $0 | Not Implemented |
UD0974 # 03 Y:2017 | 03 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,021 | $0 | Not Implemented |
UD0974 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,968 | $7,125 | Not Implemented |
WV0552 # 01 Y:2017 | 01 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $108,472 | $401,920 | Not Implemented |