Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
68,567
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
RU0130 # 05 Y:1991 | 05 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $40,632 | $16,500 | Implemented |
RU0130 # 06 Y:1991 | 06 | 1991 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,003 | $500 | Implemented |
RU0133 # 01 Y:1991 | 01 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,491 | $0 | Implemented |
RU0133 # 02 Y:1991 | 02 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,929 | $0 | Implemented |
RU0133 # 03 Y:1991 | 03 | 1991 | INSULATE BARE EQUIPMENT | $460 | $166 | Implemented |
RU0133 # 04 Y:1991 | 04 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $414 | $0 | Implemented |
RU0133 # 05 Y:1991 | 05 | 1991 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $7,014 | $11,000 | Implemented |
RU0135 # 01 Y:1991 | 01 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,125 | $0 | Implemented |
RU0135 # 02 Y:1991 | 02 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $708 | $1,860 | Implemented |
RU0135 # 04 Y:1991 | 04 | 1991 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,507 | $2,500 | Implemented |
OR0125 # 01 Y:1991 | 01 | 1991 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $18,739 | $0 | Implemented |
OR0125 # 02 Y:1991 | 02 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,392 | $6,072 | Implemented |
OR0125 # 03 Y:1991 | 03 | 1991 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,391 | $35,042 | Implemented |
OR0125 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,743 | $0 | Implemented |
OR0125 # 05 Y:1991 | 05 | 1991 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $20,934 | $83,040 | Implemented |
OR0132 # 01 Y:1991 | 01 | 1991 | INSTALL SET-BACK TIMERS | $736 | $0 | Implemented |
OR0132 # 03 Y:1991 | 03 | 1991 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $2,074 | $500 | Implemented |
OR0132 # 05 Y:1991 | 05 | 1991 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,538 | $1,000 | Implemented |
OR0132 # 06 Y:1991 | 06 | 1991 | HEAT WATER WITH EXHAUST HEAT | $6,513 | $5,744 | Implemented |
OR0132 # 07 Y:1991 | 07 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $878 | $5,922 | Implemented |
OR0132 # 08 Y:1991 | 08 | 1991 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $1,040 | $1,200 | Implemented |
OR0132 # 09 Y:1991 | 09 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $632 | $898 | Implemented |
OR0132 # 10 Y:1991 | 10 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,450 | $10,200 | Implemented |
OR0133 # 01 Y:1991 | 01 | 1991 | INSTALL SET-BACK TIMERS | $1,035 | $0 | Implemented |
OR0133 # 02 Y:1991 | 02 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $117 | $0 | Implemented |