Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
142,819
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0486 # 06 Y:2020 | 06 | 2020 | INSTALL OCCUPANCY SENSORS | $892 | $2,659 | Implemented |
AS0486 # 07 Y:2020 | 07 | 2020 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $568 | $693 | Implemented |
AS0486 # 08 Y:2020 | 08 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $381 | $132 | Implemented |
OK1025 # 01 Y:2020 | 01 | 2020 | USE RADIANT HEATER FOR SPOT HEATING | $34,672 | $127,500 | Implemented |
OK1025 # 02 Y:2020 | 02 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $3,684 | $2,420 | Implemented |
OK1025 # 03 Y:2020 | 03 | 2020 | INSULATE BARE EQUIPMENT | $5,805 | $65 | Implemented |
OK1025 # 04 Y:2020 | 04 | 2020 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $3,427 | $1,500 | Implemented |
OK1025 # 05 Y:2020 | 05 | 2020 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $1,779 | $2,207 | Not Implemented |
OK1025 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,733 | $8,651 | Implemented |
OK1025 # 07 Y:2020 | 07 | 2020 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $548 | $0 | Not Implemented |
MA0818 # 01 Y:2020 | 01 | 2020 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $4,422 | $970 | Not Implemented |
MA0818 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,320 | $9,808 | Implemented |
MA0818 # 03 Y:2020 | 03 | 2020 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $1,714 | $5,600 | Not Implemented |
MA0818 # 04 Y:2020 | 04 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $837 | $4,000 | Not Implemented |
MA0818 # 06 Y:2020 | 06 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $782 | $2,450 | Not Implemented |
MA0818 # 07 Y:2020 | 07 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $746 | $500 | Implemented |
WV0593 # 01 Y:2020 | 01 | 2020 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $16,054 | $69,828 | Implemented |
WV0593 # 02 Y:2020 | 02 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $9,611 | $20,330 | Implemented |
WV0593 # 03 Y:2020 | 03 | 2020 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,095 | $4,464 | Not Implemented |
WV0593 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,139 | $1,114 | Implemented |
WV0593 # 06 Y:2020 | 06 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,451 | $44 | Implemented |
WV0593 # 07 Y:2020 | 07 | 2020 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $2,437 | $4,000 | Not Implemented |
WV0593 # 08 Y:2020 | 08 | 2020 | DEVELOP A REPAIR/REPLACE POLICY | $1,877 | $318 | Implemented |
WV0593 # 09 Y:2020 | 09 | 2020 | INSTALL OCCUPANCY SENSORS | $1,845 | $3,682 | Implemented |
WV0593 # 10 Y:2020 | 10 | 2020 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,826 | $3,500 | Not Implemented |