IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,087

matching recommendations
Reset
ARC 2 ENERGY MANAGEMENT
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0771 # 07 Y:2007 07 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,102 $3,285 Not Implemented
UD0771 # 08 Y:2007 08 2007 INSULATE BARE EQUIPMENT $1,182 $1,450 Not Implemented
UD0771 # 09 Y:2007 09 2007 DISCONNECT BALLASTS $304 $0 Implemented
BD0337 # 01 Y:2007 01 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $927 $1,115 Not Implemented
BD0337 # 02 Y:2007 02 2007 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $14,425 $480 Implemented
BD0337 # 03 Y:2007 03 2007 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $2,084 $2,150 Not Implemented
BD0337 # 04 Y:2007 04 2007 USE SYNTHETIC LUBRICANT $228 $601 Not Implemented
BD0337 # 05 Y:2007 05 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $926 $2 Not Implemented
MZ0018 # 02 Y:2007 02 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $12,872 $0 Not Implemented
MZ0018 # 03 Y:2007 03 2007 INSTALL OCCUPANCY SENSORS $3,576 $2,450 Not Implemented
MZ0018 # 04 Y:2007 04 2007 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,001 $2,500 Not Implemented
MZ0018 # 05 Y:2007 05 2007 REDESIGN PROCESS $5,616 $0 Not Implemented
DL0009 # 01 Y:2007 01 2007 INSTALL / REPAIR INSULATION ON STEAM LINES $28,059 $10,000 Implemented
DL0009 # 02 Y:2007 02 2007 REDESIGN PROCESS $15,567 $6,300 Not Implemented
DL0009 # 03 Y:2007 03 2007 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) $11,200 $60,000 Not Implemented
DL0009 # 04 Y:2007 04 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $10,793 $11,313 Not Implemented
DL0009 # 05 Y:2007 05 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,192 $50,000 Implemented
DL0009 # 06 Y:2007 06 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,454 $0 Not Implemented
DL0009 # 07 Y:2007 07 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,890 $695 Implemented
DL0009 # 08 Y:2007 08 2007 RECOVER WASTE HEAT FROM EQUIPMENT $1,941 $590 Not Implemented
DL0009 # 09 Y:2007 09 2007 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,924 $3,809 Implemented
DL0009 # 10 Y:2007 10 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $4,500 $4,968 Not Implemented
DL0009 # 11 Y:2007 11 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,550 $20,000 Implemented
DL0009 # 12 Y:2007 12 2007 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $310 $160 Not Implemented
DL0009 # 13 Y:2007 13 2007 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $302 $10,000 Implemented