IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,571

matching recommendations
Reset
ARC 2 ENERGY MANAGEMENT
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0407 # 06 Y:2016 06 2016 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $3,031 $9,467 Not Implemented
LE0407 # 07 Y:2016 07 2016 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $8,016 $28,500 Not Implemented
OR0665 # 01 Y:2016 01 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $21,044 $11,800 Implemented
OR0665 # 02 Y:2016 02 2016 FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM $88,324 $19,650 Not Implemented
OR0665 # 03 Y:2016 03 2016 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $3,107 $1,025 Not Implemented
OR0665 # 04 Y:2016 04 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,140 $7,325 Not Implemented
OR0665 # 05 Y:2016 05 2016 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,434 $0 Implemented
UD0939 # 01 Y:2016 01 2016 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,169 $0 Implemented
UD0939 # 02 Y:2016 02 2016 COMBINE UTILITY METERS $10,737 $0 Not Implemented
UD0939 # 04 Y:2016 04 2016 RECOVER WASTE HEAT FROM EQUIPMENT $4,358 $400 Not Implemented
UD0939 # 05 Y:2016 05 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,740 $1,000 Implemented
UD0939 # 06 Y:2016 06 2016 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $164 $375 Implemented
UD0939 # 07 Y:2016 07 2016 INSTALL OCCUPANCY SENSORS $1,588 $1,013 Implemented
UD0939 # 08 Y:2016 08 2016 INSTALL SPECTRAL REFLECTORS / DELAMP $1,699 $315 Implemented
UD0939 # 09 Y:2016 09 2016 COVER OPEN TANKS $1,526 $740 Not Implemented
UD0939 # 10 Y:2016 10 2016 COVER OPEN TANKS $612 $600 Not Implemented
UD0939 # 11 Y:2016 11 2016 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $1,321 $6,500 Not Implemented
OR0664 # 01 Y:2016 01 2016 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $2,739 $0 Not Implemented
OR0664 # 02 Y:2016 02 2016 INSULATE BARE EQUIPMENT $1,310 $2,584 Not Implemented
OR0664 # 03 Y:2016 03 2016 INSTALL SPECTRAL REFLECTORS / DELAMP $12,507 $32,393 Implemented
OR0664 # 04 Y:2016 04 2016 UPGRADE CONVEYORS $74,609 $242,718 Not Implemented