Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
147,636
matching recommendationsARC | 2. | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0604 # 02 Y:2023 | 02 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $30,577 | $37,582 | Implemented |
UF0604 # 03 Y:2023 | 03 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $8,590 | $37,275 | Implemented |
UF0604 # 04 Y:2023 | 04 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,173 | $0 | Implemented |
UF0604 # 05 Y:2023 | 05 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,430 | $780 | Implemented |
UF0604 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,334 | $6,383 | Not Implemented |
LT8385 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,025 | $705 | n/a |
LT8385 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,834 | $7,403 | n/a |
WM0208 # 01 Y:2024 | 01 | 2024 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $37,878 | $122,100 | Not Implemented |
WM0208 # 02 Y:2024 | 02 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $9,702 | $8,700 | Implemented |
WM0208 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,761 | $1,950 | Implemented |
WM0208 # 04 Y:2024 | 04 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,796 | $0 | Not Implemented |
WM0208 # 05 Y:2024 | 05 | 2024 | USE COMPRESSOR AIR FILTERS | $3,395 | $4,786 | Not Implemented |
WM0208 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,014 | $4,664 | Implemented |
WM0208 # 07 Y:2024 | 07 | 2024 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $430 | $700 | Implemented |
UU0238 # 01 Y:2024 | 01 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $13,223 | $4,080 | Implemented |
UU0238 # 02 Y:2024 | 02 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,624 | $12,621 | Implemented |
UU0238 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $7,670 | $22,500 | Not Implemented |
UU0238 # 04 Y:2024 | 04 | 2024 | CLEAN CONDENSER TUBES | $3,894 | $3,890 | Implemented |
UU0238 # 05 Y:2024 | 05 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,731 | $5,916 | Implemented |
UA0279 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $1,228 | $2,262 | Implemented |
UA0279 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,676 | $8,591 | Implemented |
UA0279 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,760 | $1,000 | Implemented |
UA0279 # 04 Y:2023 | 04 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $3,760 | $1,407 | Implemented |
UA0279 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,977 | $7,874 | Not Implemented |
UA0279 # 06 Y:2023 | 06 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,016 | $384 | Not Implemented |