Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,019
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0788 # 06 Y:2019 | 06 | 2019 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $860 | $124 | Implemented |
AM0787 # 01 Y:2019 | 01 | 2019 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $290,927 | $1,011,274 | Not Implemented |
AM0787 # 02 Y:2019 | 02 | 2019 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $312,044 | $849,614 | Not Implemented |
AM0787 # 03 Y:2019 | 03 | 2019 | REPAIR OR REPLACE STEAM TRAPS | $56,595 | $10,440 | Implemented |
AM0787 # 04 Y:2019 | 04 | 2019 | USE SYNTHETIC LUBRICANT | $13,271 | $14,560 | Implemented |
AM0787 # 05 Y:2019 | 05 | 2019 | OPTIMIZE PLANT POWER FACTOR | $70,814 | $178,864 | Implemented |
AM0787 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,322 | $825 | Implemented |
AM0787 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,577 | $2,640 | Implemented |
AM0787 # 08 Y:2019 | 08 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $399 | $280 | Not Implemented |
AM0786 # 01 Y:2019 | 01 | 2019 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $55,800 | $67,044 | Implemented |
AM0786 # 02 Y:2019 | 02 | 2019 | OPTIMIZE PLANT POWER FACTOR | $11,700 | $15,300 | Implemented |
AM0786 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,750 | $22,600 | Implemented |
AM0786 # 04 Y:2019 | 04 | 2019 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,760 | $4,570 | Implemented |
AM0786 # 05 Y:2019 | 05 | 2019 | USE SYNTHETIC LUBRICANT | $910 | $290 | Implemented |
AM0785 # 01 Y:2019 | 01 | 2019 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $19,800 | $750 | Not Implemented |
AM0785 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,450 | $18,920 | Implemented |
AM0785 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,880 | $2,000 | Implemented |
AM0785 # 04 Y:2019 | 04 | 2019 | OPTIMIZE PLANT POWER FACTOR | $4,685 | $6,865 | Implemented |
AM0785 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,470 | $460 | Not Implemented |
AM0785 # 06 Y:2019 | 06 | 2019 | OPTIMIZE PLANT POWER FACTOR | $1,340 | $5,250 | Not Implemented |
AM0785 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,160 | $650 | Not Implemented |
AM0785 # 08 Y:2019 | 08 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $620 | $20 | Implemented |
AM0785 # 09 Y:2019 | 09 | 2019 | INSTALL SKYLIGHTS | $440 | $0 | Not Implemented |
AM0784 # 01 Y:2019 | 01 | 2019 | OPTIMIZE PLANT POWER FACTOR | $27,050 | $32,150 | Implemented |
AM0784 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $32,100 | $8,000 | Implemented |