Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,391
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0471 # 08 Y:2015 | 08 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $356 | $20 | Not Implemented |
BD0471 # 09 Y:2015 | 09 | 2015 | REVISE RAW MATERIAL SPECS | $90,750 | $7,000 | Not Implemented |
BD0471 # 10 Y:2015 | 10 | 2015 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $86,400 | $1,050 | Implemented |
BD0470 # 01 Y:2015 | 01 | 2015 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $26,090 | $30,000 | Not Implemented |
BD0470 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,593 | $7,220 | Not Implemented |
BD0470 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,298 | $5,241 | Not Implemented |
BD0470 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,232 | $500 | Not Implemented |
BD0470 # 05 Y:2015 | 05 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,984 | $2,500 | Not Implemented |
BD0470 # 06 Y:2015 | 06 | 2015 | USE PHOTOCELL CONTROLS | $1,063 | $950 | Not Implemented |
BD0470 # 07 Y:2015 | 07 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,041 | $20 | Not Implemented |
BD0470 # 08 Y:2015 | 08 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $997 | $450 | Not Implemented |
BD0470 # 09 Y:2015 | 09 | 2015 | INSTALL OCCUPANCY SENSORS | $911 | $1,575 | Not Implemented |
BD0470 # 10 Y:2015 | 10 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $305 | $450 | Not Implemented |
BD0470 # 11 Y:2015 | 11 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $185 | $200 | Not Implemented |
BD0469 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $761 | $455 | Implemented |
BD0469 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $681 | $20 | Not Implemented |
BD0469 # 06 Y:2015 | 06 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $623 | $700 | Not Implemented |
BD0469 # 07 Y:2015 | 07 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $591 | $1,000 | Not Implemented |
BD0469 # 08 Y:2015 | 08 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $290 | $1,000 | Not Implemented |
BD0469 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $177 | $176 | Not Implemented |
BD0469 # 10 Y:2015 | 10 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $56 | $150 | Not Implemented |
BD0469 # 11 Y:2015 | 11 | 2015 | REUSE / RECYCLE/ SELL RUBBER PRODUCTS | $4,000 | $100 | Implemented |
BD0469 # 01 Y:2015 | 01 | 2015 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $2,898 | $4,090 | Not Implemented |
BD0469 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,562 | $4,770 | Not Implemented |
BD0469 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $2,198 | $750 | Not Implemented |