Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,391
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0296 # 06 Y:2005 | 06 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,160 | $600 | Implemented |
BD0296 # 07 Y:2005 | 07 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $924 | $500 | Not Implemented |
BD0296 # 08 Y:2005 | 08 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $846 | $650 | Implemented |
BD0296 # 09 Y:2005 | 09 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $499 | $0 | Not Implemented |
BD0296 # 10 Y:2005 | 10 | 2005 | USE AN ALTERNATIVE DESULFURIZING AGENT TO ELIMINATE HAZARDOUS SLAG FORMATION | $192,926 | $3,000 | Implemented |
BD0293 # 01 Y:2005 | 01 | 2005 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $14,847 | $2,400 | Implemented |
BD0293 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,468 | $5,250 | Not Implemented |
BD0293 # 03 Y:2005 | 03 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $824 | $2,100 | Implemented |
BD0293 # 04 Y:2005 | 04 | 2005 | INSTALL OCCUPANCY SENSORS | $1,306 | $1,125 | Implemented |
BD0293 # 05 Y:2005 | 05 | 2005 | USE POWER DURING OFF-PEAK PERIODS | $950 | $1,700 | Implemented |
BD0293 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $740 | $700 | Implemented |
BD0293 # 07 Y:2005 | 07 | 2005 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $4,251 | $1,250 | Implemented |
BD0293 # 08 Y:2005 | 08 | 2005 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,306 | $3,500 | Not Implemented |
BD0295 # 01 Y:2005 | 01 | 2005 | AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED | $32,765 | $600 | Implemented |
BD0295 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,254 | $8,470 | Implemented |
BD0295 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,391 | $900 | Implemented |
BD0295 # 04 Y:2005 | 04 | 2005 | INSTALL OCCUPANCY SENSORS | $14,253 | $2,875 | Implemented |
BD0295 # 05 Y:2005 | 05 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,487 | $3,000 | Implemented |
BD0295 # 06 Y:2005 | 06 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,724 | $0 | Implemented |
BD0295 # 07 Y:2005 | 07 | 2005 | INSULATE BARE EQUIPMENT | $423 | $0 | Implemented |
BD0294 # 01 Y:2005 | 01 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,821 | $400 | Implemented |
BD0294 # 02 Y:2005 | 02 | 2005 | INSTALL OCCUPANCY SENSORS | $1,291 | $750 | Not Implemented |
BD0294 # 03 Y:2005 | 03 | 2005 | INSULATE BARE EQUIPMENT | $599 | $263 | Implemented |
BD0294 # 04 Y:2005 | 04 | 2005 | INSTALL AUTOMATIC PACKING EQUIPMENT | $41,600 | $22,000 | Implemented |
BD0294 # 05 Y:2005 | 05 | 2005 | EXPAND OPERATIONS INTO UNUSED SPACE | $40,952 | $20,000 | Implemented |