Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
374
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CI0032 # 08 Y:2024 | 08 | 2024 | INSTALL OCCUPANCY SENSORS | $1,100 | $2,025 | n/a |
CI0032 # 07 Y:2024 | 07 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,346 | $100 | n/a |
CI0032 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,536 | $22,885 | n/a |
CI0032 # 05 Y:2024 | 05 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,401 | $0 | n/a |
CI0032 # 04 Y:2024 | 04 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $8,168 | $13,563 | n/a |
CI0032 # 03 Y:2024 | 03 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $9,326 | $24,000 | n/a |
CI0032 # 02 Y:2024 | 02 | 2024 | INSULATE BARE EQUIPMENT | $10,726 | $2,419 | n/a |
CI0032 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $47,412 | $313,000 | n/a |
CI0031 # 09 Y:2024 | 09 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $835 | $400 | n/a |
CI0031 # 08 Y:2024 | 08 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,321 | $1,928 | n/a |
CI0031 # 07 Y:2024 | 07 | 2024 | INSTALL OCCUPANCY SENSORS | $2,443 | $1,800 | n/a |
CI0031 # 06 Y:2024 | 06 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,563 | $100 | n/a |
CI0031 # 05 Y:2024 | 05 | 2024 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $2,757 | $20,000 | n/a |
CI0031 # 04 Y:2024 | 04 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $8,940 | $67,000 | n/a |
CI0031 # 03 Y:2024 | 03 | 2024 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $8,942 | $30,000 | n/a |
CI0031 # 02 Y:2024 | 02 | 2024 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $25,325 | $20,000 | n/a |
CI0031 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $37,344 | $306,517 | n/a |
CI0030 # 05 Y:2024 | 05 | 2024 | INSULATE BARE EQUIPMENT | $4,265 | $2,565 | n/a |
CI0030 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,581 | $101,332 | n/a |
CI0030 # 02 Y:2024 | 02 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $15,868 | $1,600 | n/a |
CI0030 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $8,384 | $3,000 | n/a |
CI0030 # 04 Y:2024 | 04 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $4,601 | $18,900 | n/a |
CI0030 # 06 Y:2024 | 06 | 2024 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,914 | $1,600 | n/a |
CI0030 # 07 Y:2024 | 07 | 2024 | USE PHOTOCELL CONTROLS | $3,830 | $1,500 | n/a |
CI0030 # 08 Y:2024 | 08 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $2,431 | $4,000 | n/a |