Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
41
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CL1808 # 04 Y:2018 | 04 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $310 | $0 | Not Implemented |
CL1808 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,135 | $2,080 | Not Implemented |
CL1808 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,697 | $3,911 | Not Implemented |
CL1808 # 01 Y:2018 | 01 | 2018 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $8,900 | $250 | Not Implemented |
CL1809 # 03 Y:2018 | 03 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,401 | $900 | Not Implemented |
CL1809 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,602 | $11,662 | Implemented |
CL1809 # 01 Y:2018 | 01 | 2018 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $21,846 | $250 | Implemented |
CL1807 # 03 Y:2018 | 03 | 2018 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $13,718 | $15,500 | Not Implemented |
CL1807 # 01 Y:2018 | 01 | 2018 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $51,068 | $500 | Not Implemented |
CL1807 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $38,713 | $42,563 | Not Implemented |
CL1807 # 04 Y:2018 | 04 | 2018 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $3,717 | $3,050 | Not Implemented |
CL1807 # 05 Y:2018 | 05 | 2018 | REPLACE BOILER | $1,478 | $750 | Not Implemented |
CL1806 # 06 Y:2018 | 06 | 2018 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $6,909 | $0 | Implemented |
CL1806 # 05 Y:2018 | 05 | 2018 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $7,271 | $4,700 | Not Implemented |
CL1806 # 04 Y:2018 | 04 | 2018 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $23,451 | $12,200 | Not Implemented |
CL1806 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $34,631 | $52,880 | Implemented |
CL1806 # 02 Y:2018 | 02 | 2018 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $45,354 | $46,500 | Not Implemented |
CL1806 # 01 Y:2018 | 01 | 2018 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $66,598 | $22,500 | Not Implemented |
CL1805 # 01 Y:2018 | 01 | 2018 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $50,691 | $506,862 | Implemented |
CL1805 # 03 Y:2018 | 03 | 2018 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $637 | $2,500 | Not Implemented |
CL1805 # 02 Y:2018 | 02 | 2018 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,183 | $13,011 | Implemented |
CL1804 # 05 Y:2018 | 05 | 2018 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $34,121 | $34,121 | Not Implemented |
CL1804 # 04 Y:2018 | 04 | 2018 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $39,409 | $3,050 | Implemented |
CL1804 # 03 Y:2018 | 03 | 2018 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $42,335 | $15,500 | Not Implemented |
CL1804 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46,306 | $184,601 | Implemented |