Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,456
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0062 # 04 Y:1986 | 04 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,765 | $3,300 | Not Implemented |
CO0062 # 05 Y:1986 | 05 | 1986 | IMPROVE LUBRICATION PRACTICES | $3,995 | $0 | Implemented |
CO0062 # 06 Y:1986 | 06 | 1986 | REPAIR AND ELIMINATE STEAM LEAKS | $3,931 | $200 | Implemented |
CO0062 # 07 Y:1986 | 07 | 1986 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $1,953 | $2,824 | Not Implemented |
CO0062 # 08 Y:1986 | 08 | 1986 | INSTALL TURBULATORS | $947 | $750 | Not Implemented |
CO0062 # 09 Y:1986 | 09 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $934 | $200 | Implemented |
CO0062 # 10 Y:1986 | 10 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $491 | $300 | Implemented |
CO0062 # 11 Y:1986 | 11 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $584 | $20 | Not Implemented |
CO0062 # 12 Y:1986 | 12 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,862 | $627 | Implemented |
CO0075 # 01 Y:1986 | 01 | 1986 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $9,363 | $10,500 | Not Implemented |
CO0075 # 02 Y:1986 | 02 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,439 | $300 | Not Implemented |
CO0075 # 03 Y:1986 | 03 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,707 | $10,000 | Not Implemented |
CO0075 # 04 Y:1986 | 04 | 1986 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $14,637 | $10,000 | Not Implemented |
CO0075 # 05 Y:1986 | 05 | 1986 | IMPROVE LUBRICATION PRACTICES | $12,489 | $0 | Not Implemented |
CO0075 # 06 Y:1986 | 06 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,024 | $700 | Not Implemented |
CO0075 # 07 Y:1986 | 07 | 1986 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,935 | $800 | Not Implemented |
CO0075 # 08 Y:1986 | 08 | 1986 | USE RADIANT HEATER FOR SPOT HEATING | $3,692 | $9,100 | Not Implemented |
CO0075 # 09 Y:1986 | 09 | 1986 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,606 | $12,000 | Not Implemented |
CO0075 # 10 Y:1986 | 10 | 1986 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $366 | $892 | Not Implemented |
CO0075 # 11 Y:1986 | 11 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,813 | $903 | Not Implemented |
CO0076 # 01 Y:1986 | 01 | 1986 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $3,878 | $200 | Implemented |
CO0076 # 02 Y:1986 | 02 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $648 | $300 | Implemented |
CO0076 # 03 Y:1986 | 03 | 1986 | USE RADIANT HEATER FOR SPOT HEATING | $2,349 | $7,000 | Implemented |
CO0076 # 04 Y:1986 | 04 | 1986 | IMPROVE LUBRICATION PRACTICES | $2,455 | $0 | Not Implemented |
CO0076 # 05 Y:1986 | 05 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,455 | $2,400 | Implemented |