Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,456
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0430 # 02 Y:1998 | 02 | 1998 | INSTALL TURBULATORS | $1,770 | $5,750 | Not Implemented |
CO0430 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,470 | $1,280 | Implemented |
CO0430 # 04 Y:1998 | 04 | 1998 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $-210 | $2,000 | Implemented |
CO0430 # 05 Y:1998 | 05 | 1998 | SELL COMBUSTIBLE WASTE | $15,970 | $56,700 | Implemented |
CO0430 # 06 Y:1998 | 06 | 1998 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $674,900 | $1,645,000 | Not Implemented |
CO0429 # 01 Y:1998 | 01 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $840 | $1,000 | Implemented |
CO0429 # 02 Y:1998 | 02 | 1998 | CLOSELY MONITOR CHEMICAL ADDITIONS TO INCREASE BATH LIFE | $4,860 | $0 | Implemented |
CO0429 # 03 Y:1998 | 03 | 1998 | ALLOW DRAINAGE BEFORE WITHDRAWING OBJECT | $2,930 | $800 | Not Implemented |
CO0429 # 04 Y:1998 | 04 | 1998 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $6,000 | $10,160 | Implemented |
CO0429 # 05 Y:1998 | 05 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $730 | $280 | Not Implemented |
CO0428 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,428 | $8,036 | Not Implemented |
CO0428 # 02 Y:1998 | 02 | 1998 | DISCONNECT BALLASTS | $3,050 | $350 | Not Implemented |
CO0428 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $470 | $50 | Not Implemented |
CO0428 # 04 Y:1998 | 04 | 1998 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $500 | $1,750 | Not Implemented |
CO0427 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $500 | $2,082 | Implemented |
CO0427 # 02 Y:1998 | 02 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $290 | $1,000 | Implemented |
CO0427 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $240 | $40 | Implemented |
CO0427 # 04 Y:1998 | 04 | 1998 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $210 | $0 | Not Implemented |
CO0427 # 05 Y:1998 | 05 | 1998 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $34,700 | $300,000 | Not Implemented |
CO0427 # 06 Y:1998 | 06 | 1998 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $6,080 | $30,000 | Not Implemented |
CO0427 # 07 Y:1998 | 07 | 1998 | MAINTAIN/ENLARGE A STOCK OF SPARE PARTS | $18,250 | $27,000 | Implemented |
CO0426 # 01 Y:1998 | 01 | 1998 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $8,960 | $5,700 | Implemented |
CO0426 # 02 Y:1998 | 02 | 1998 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,390 | $9,870 | Implemented |
CO0426 # 03 Y:1998 | 03 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $9,590 | $25,000 | Not Implemented |
CO0426 # 04 Y:1998 | 04 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,420 | $4,303 | Implemented |