Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
50
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CW0126 # 07 Y:2022 | 07 | 2022 | USE SOLAR HEAT FOR HEAT | $2,171 | $13,500 | n/a |
CW0126 # 06 Y:2022 | 06 | 2022 | USE POWER DURING OFF-PEAK PERIODS | $921 | $0 | n/a |
CW0126 # 05 Y:2022 | 05 | 2022 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $10,872 | $33,000 | n/a |
CW0126 # 04 Y:2022 | 04 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $19,047 | $54,963 | n/a |
CW0126 # 01 Y:2022 | 01 | 2022 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $17,675 | $20,960 | n/a |
CW0126 # 03 Y:2022 | 03 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $361 | $0 | n/a |
CW0126 # 02 Y:2022 | 02 | 2022 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $12,461 | $15,547 | n/a |
CW0125 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,007 | $17,900 | n/a |
CW0125 # 06 Y:2022 | 06 | 2022 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $70,112 | $8,000 | n/a |
CW0125 # 05 Y:2022 | 05 | 2022 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $23,398 | $56,000 | n/a |
CW0125 # 04 Y:2022 | 04 | 2022 | USE SYNTHETIC LUBRICANT | $18,816 | $9,059 | n/a |
CW0125 # 08 Y:2022 | 08 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,307 | $41,871 | n/a |
CW0125 # 07 Y:2022 | 07 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,449 | $25,995 | n/a |
CW0125 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,655 | $2,019 | n/a |
CW0125 # 03 Y:2022 | 03 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $37,427 | $1,156 | n/a |
CW0124 # 07 Y:2022 | 07 | 2022 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $1,505 | $2,582 | n/a |
CW0124 # 04 Y:2022 | 04 | 2022 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $7,380 | $0 | n/a |
CW0124 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $929 | $1,866 | n/a |
CW0124 # 01 Y:2022 | 01 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,407 | $100 | n/a |
CW0124 # 03 Y:2022 | 03 | 2022 | USER BATTERY STORAGE FOR POWER QUALITY ISSUES | $230,341 | $287,555 | n/a |
CW0124 # 05 Y:2022 | 05 | 2022 | MODIFY WORKLOAD | $16,860 | $0 | n/a |
CW0124 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,378 | $47,373 | n/a |
CW0123 # 05 Y:2022 | 05 | 2022 | USE OPTIMUM TEMPERATURE | $4,521 | $3,500 | n/a |
CW0123 # 06 Y:2022 | 06 | 2022 | SCHEDULE BAKING TIMES OF SMALL AND LARGE COMPONENTS | $2,357 | $0 | n/a |
CW0123 # 07 Y:2022 | 07 | 2022 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $30,793 | $45,000 | n/a |