Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
273
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0745 # 09 Y:2003 | 09 | 2003 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $43,576 | $51,000 | n/a |
GT0764 # 03 Y:2003 | 03 | 2003 | COVER OPEN TANKS | $7,550 | $2,505 | Not Implemented |
GT0764 # 08 Y:2003 | 08 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,368 | $36,246 | Implemented |
GT0764 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,150 | $5,635 | Implemented |
GT0764 # 06 Y:2003 | 06 | 2003 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $17,500 | $38,000 | Not Implemented |
GT0764 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,750 | $710 | Implemented |
GT0764 # 04 Y:2003 | 04 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $620 | $1,555 | Implemented |
GT0764 # 02 Y:2003 | 02 | 2003 | USE SYNTHETIC LUBRICANT | $1,055 | $0 | Not Implemented |
GT0764 # 01 Y:2003 | 01 | 2003 | COVER OPEN TANKS | $17,200 | $0 | Implemented |
GT0763 # 03 Y:2003 | 03 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $696 | $1,680 | Not Implemented |
GT0763 # 04 Y:2003 | 04 | 2003 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $81 | $110 | Implemented |
GT0763 # 05 Y:2003 | 05 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,266 | $11,300 | Not Implemented |
GT0763 # 06 Y:2003 | 06 | 2003 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,086 | $7,250 | Not Implemented |
GT0763 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,795 | $12,447 | Not Implemented |
GT0763 # 02 Y:2003 | 02 | 2003 | KEEP EQUIPMENT CLEAN | $655 | $0 | Implemented |
GT0763 # 01 Y:2003 | 01 | 2003 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $8,000 | $1,350 | Implemented |
GT0763 # 11 Y:2003 | 11 | 2003 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $8,026 | $1,500 | Not Implemented |
GT0763 # 10 Y:2003 | 10 | 2003 | CONTROL PRESSURE ON STEAMER OPERATIONS | $11,010 | $5,823 | Not Implemented |
GT0763 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $536 | $5,146 | Implemented |
GT0763 # 08 Y:2003 | 08 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,503 | $19,339 | Implemented |
GT0762 # 02 Y:2003 | 02 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $12,813 | $700 | Implemented |
GT0762 # 11 Y:2003 | 11 | 2003 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $210,205 | $2,700,000 | Not Implemented |
GT0762 # 01 Y:2003 | 01 | 2003 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $153,000 | $0 | Not Implemented |
GT0762 # 08 Y:2003 | 08 | 2003 | INCREASE AMOUNT OF CONDENSATE RETURNED | $18,580 | $19,500 | Not Implemented |
GT0762 # 06 Y:2003 | 06 | 2003 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,390 | $0 | Not Implemented |