Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,349
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0422 # 08 Y:2008 | 08 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,350 | $0 | Implemented |
IA0422 # 09 Y:2008 | 09 | 2008 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $474 | $143 | Implemented |
IA0422 # 11 Y:2008 | 11 | 2008 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $664 | $250 | Implemented |
IA0422 # 12 Y:2008 | 12 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,301 | $0 | Implemented |
IA0421 # 01 Y:2007 | 01 | 2007 | REPAIR AND ELIMINATE STEAM LEAKS | $5,499 | $675 | Implemented |
IA0421 # 03 Y:2007 | 03 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $950 | $2,575 | Implemented |
IA0421 # 04 Y:2007 | 04 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,109 | $4,080 | Implemented |
IA0421 # 05 Y:2007 | 05 | 2007 | MODIFY STARTUP/SHUTDOWN TIMES | $2,951 | $500 | Implemented |
IA0421 # 06 Y:2007 | 06 | 2007 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $2,749 | $60 | Implemented |
IA0421 # 07 Y:2007 | 07 | 2007 | IMPROVE COMBUSTION CONTROL CAPABILITY | $1,093 | $1,800 | Implemented |
IA0421 # 08 Y:2007 | 08 | 2007 | MINIMIZE WATER USAGE | $10,056 | $400 | Implemented |
IA0419 # 02 Y:2007 | 02 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $678 | $25 | Implemented |
IA0419 # 03 Y:2007 | 03 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,055 | $500 | Implemented |
IA0419 # 05 Y:2007 | 05 | 2007 | INSTALL OCCUPANCY SENSORS | $758 | $1,001 | Implemented |
IA0419 # 07 Y:2007 | 07 | 2007 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,450 | $1,200 | Implemented |
IA0419 # 09 Y:2007 | 09 | 2007 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,583 | $3,300 | Implemented |
IA0419 # 10 Y:2007 | 10 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,325 | $800 | Implemented |
IA0418 # 01 Y:2008 | 01 | 2008 | INSULATE BARE EQUIPMENT | $456 | $252 | Implemented |
IA0418 # 02 Y:2008 | 02 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $228 | $244 | Implemented |
IA0418 # 03 Y:2008 | 03 | 2008 | INSTALL OCCUPANCY SENSORS | $845 | $770 | Implemented |
IA0418 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,939 | $20,513 | Implemented |
IA0418 # 06 Y:2008 | 06 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,589 | $24 | Implemented |
IA0418 # 07 Y:2008 | 07 | 2008 | REPAIR AND ELIMINATE STEAM LEAKS | $2,001 | $788 | Implemented |
IA0418 # 08 Y:2008 | 08 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,360 | $1,100 | Implemented |
IA0416 # 01 Y:2007 | 01 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,435 | $1,000 | Implemented |