Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
117
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0445 # 03 Y:2009 | 03 | 2009 | INSTALL OCCUPANCY SENSORS | $1,603 | $4,551 | Not Implemented |
IA0445 # 04 Y:2009 | 04 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,460 | $100 | Not Implemented |
IA0445 # 05 Y:2009 | 05 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,180 | $560 | Not Implemented |
IA0445 # 06 Y:2009 | 06 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,637 | $506 | Not Implemented |
IA0445 # 07 Y:2009 | 07 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,414 | $25 | Not Implemented |
IA0445 # 08 Y:2009 | 08 | 2009 | REDUCE VENTILATION AIR | $18,248 | $20,000 | Not Implemented |
IA0445 # 09 Y:2009 | 09 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $450 | $134 | Not Implemented |
IA0433 # 01 Y:2008 | 01 | 2008 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $52,036 | $0 | Not Implemented |
IA0433 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,622 | $459 | Implemented |
IA0433 # 03 Y:2008 | 03 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,886 | $832 | Implemented |
IA0433 # 04 Y:2008 | 04 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,195 | $54 | Implemented |
IA0433 # 05 Y:2008 | 05 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $13,871 | $1,700 | Not Implemented |
IA0433 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,324 | $37,346 | Not Implemented |
IA0433 # 07 Y:2008 | 07 | 2008 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $3,364 | $4,000 | Implemented |
IA0433 # 08 Y:2008 | 08 | 2008 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $587 | $142 | Implemented |
IA0433 # 09 Y:2008 | 09 | 2008 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $7,158 | $4,624 | Not Implemented |
IA0433 # 10 Y:2008 | 10 | 2008 | INSULATE BARE EQUIPMENT | $524 | $254 | Not Implemented |
IA0433 # 11 Y:2008 | 11 | 2008 | ADJUST VENTS TO MINIMIZE ENERGY USE | $3,380 | $294 | Implemented |
IA0357 # 01 Y:2004 | 01 | 2004 | OPTIMIZE PLANT POWER FACTOR | $1,879 | $2,445 | Implemented |
IA0357 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,225 | $349 | Implemented |
IA0357 # 03 Y:2004 | 03 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,125 | $25 | Not Implemented |
IA0357 # 04 Y:2004 | 04 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $657 | $262 | Implemented |
IA0357 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,027 | $23 | Implemented |
IA0357 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $447 | $654 | Implemented |
IA0357 # 07 Y:2004 | 07 | 2004 | INSTALL REFRIGERATION SYSTEM TO COOL PRODUCT | $206,874 | $145,850 | Implemented |