Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,344
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0127 # 12 Y:1984 | 12 | 1984 | REPAIR AND ELIMINATE STEAM LEAKS | $187 | $60 | Implemented |
KU0125 # 01 Y:1984 | 01 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $3,948 | $0 | Implemented |
KU0121 # 01 Y:1984 | 01 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $8,835 | $0 | Implemented |
KU0121 # 03 Y:1984 | 03 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,383 | $2,250 | Implemented |
KU0121 # 04 Y:1984 | 04 | 1984 | INSULATE BARE EQUIPMENT | $3,959 | $1,000 | Implemented |
KU0121 # 06 Y:1984 | 06 | 1984 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $2,034 | $738 | Implemented |
KU0121 # 07 Y:1984 | 07 | 1984 | USE MINIMUM SAFE OVEN VENTILATION | $474 | $0 | Implemented |
KU0121 # 09 Y:1984 | 09 | 1984 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $835 | $1,200 | Implemented |
KU0121 # 11 Y:1984 | 11 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $298 | $100 | Implemented |
KU0122 # 02 Y:1984 | 02 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,060 | $5,000 | Implemented |
KU0122 # 03 Y:1984 | 03 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,649 | $3,690 | Implemented |
KU0122 # 04 Y:1984 | 04 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $3,254 | $450 | Implemented |
KU0122 # 05 Y:1984 | 05 | 1984 | KEEP BOILER TUBES CLEAN | $1,926 | $2,000 | Implemented |
KU0122 # 07 Y:1984 | 07 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,439 | $1,985 | Implemented |
KU0122 # 08 Y:1984 | 08 | 1984 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $423 | $0 | Implemented |
KU0122 # 09 Y:1984 | 09 | 1984 | INSTALL SET-BACK TIMERS | $401 | $50 | Implemented |
KU0122 # 10 Y:1984 | 10 | 1984 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $272 | $280 | Implemented |
KU0122 # 11 Y:1984 | 11 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $211 | $300 | Implemented |
KU0122 # 12 Y:1984 | 12 | 1984 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $169 | $0 | Implemented |
KU0123 # 02 Y:1984 | 02 | 1984 | INSULATE BARE EQUIPMENT | $522 | $100 | Implemented |
KU0123 # 03 Y:1984 | 03 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14 | $20 | Implemented |
KU0123 # 05 Y:1984 | 05 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $112 | $100 | Implemented |
KU0123 # 06 Y:1984 | 06 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $44 | $150 | Implemented |
KU0124 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,060 | $1,800 | Implemented |
KU0124 # 02 Y:1984 | 02 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,287 | $2,200 | Implemented |