IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,867

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MI0125 # 03 Y:2006 03 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $32,634 $35,000 Implemented
MI0125 # 04 Y:2006 04 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $24,438 $1,074 Implemented
MI0125 # 05 Y:2006 05 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $9,589 $850 Implemented
MI0125 # 07 Y:2006 07 2006 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $4,013 $395 Implemented
MI0123 # 02 Y:2006 02 2006 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $14,670 $84 Implemented
MI0123 # 04 Y:2006 04 2006 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,583 $140 Implemented
MI0123 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,702 $1,018 Implemented
MI0123 # 06 Y:2006 06 2006 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $845 $660 Implemented
MI0123 # 07 Y:2006 07 2006 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $405 $0 Implemented
MI0123 # 08 Y:2006 08 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $403 $335 Implemented
MI0123 # 09 Y:2006 09 2006 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $290 $24 Implemented
MI0123 # 10 Y:2006 10 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $201 $0 Implemented
MI0121 # 01 Y:2006 01 2006 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $5,669 $0 Implemented
MI0121 # 03 Y:2006 03 2006 INSULATE BARE EQUIPMENT $2,209 $420 Implemented
MI0121 # 04 Y:2006 04 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,015 $964 Implemented
MI0119 # 01 Y:2005 01 2005 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $9,064 $170 Implemented
MI0119 # 02 Y:2005 02 2005 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $6,450 $96 Implemented
MI0119 # 04 Y:2005 04 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,973 $862 Implemented
MI0119 # 05 Y:2005 05 2005 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $1,003 $22 Implemented
MI0119 # 07 Y:2005 07 2005 USE SYNTHETIC LUBRICANT $714 $52 Implemented
MI0117 # 01 Y:2005 01 2005 TURN OFF EQUIPMENT WHEN NOT IN USE $16,898 $1,350 Implemented
MI0117 # 02 Y:2005 02 2005 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $4,463 $11,400 Implemented
MI0117 # 03 Y:2005 03 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,012 $906 Implemented
MI0116 # 01 Y:2005 01 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,754 $2,512 Implemented
MI0116 # 03 Y:2005 03 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,648 $1,074 Implemented