Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
162
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0232 # 03 Y:2002 | 03 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $1,645 | $1,818 | Implemented |
NC0232 # 04 Y:2002 | 04 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $561 | $248 | Implemented |
NC0232 # 05 Y:2002 | 05 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $740 | $150 | Implemented |
NC0232 # 06 Y:2002 | 06 | 2002 | KEEP BOILER TUBES CLEAN | $596 | $1,100 | Not Implemented |
NC0232 # 07 Y:2002 | 07 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,486 | $850 | Implemented |
NC0231 # 01 Y:2002 | 01 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $2,088 | $2,383 | Not Implemented |
NC0231 # 02 Y:2002 | 02 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $324 | $736 | Not Implemented |
NC0231 # 03 Y:2002 | 03 | 2002 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,818 | $830 | Not Implemented |
NC0231 # 04 Y:2002 | 04 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,994 | $200 | Not Implemented |
NC0231 # 05 Y:2002 | 05 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,626 | $0 | Implemented |
NC0233 # 01 Y:2002 | 01 | 2002 | BURN WOOD BY-PRODUCTS FOR HEAT | $55,321 | $109,000 | n/a |
NC0233 # 02 Y:2002 | 02 | 2002 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $6,359 | $2,000 | Implemented |
NC0233 # 03 Y:2002 | 03 | 2002 | IMPROVE SPACE COMFORT CONDITIONING | $75,150 | $10,000 | Implemented |
NC0233 # 04 Y:2002 | 04 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $293 | $778 | Implemented |
NC0233 # 05 Y:2002 | 05 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $186 | $289 | Not Implemented |
NC0229 # 01 Y:2002 | 01 | 2002 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $51,728 | $50,000 | Implemented |
NC0229 # 02 Y:2002 | 02 | 2002 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $55,158 | $15,000 | Implemented |
NC0229 # 03 Y:2002 | 03 | 2002 | KEEP EQUIPMENT CLEAN | $21,155 | $1,000 | Implemented |
NC0229 # 04 Y:2002 | 04 | 2002 | INSULATE BARE EQUIPMENT | $5,620 | $1,577 | Not Implemented |
NC0229 # 05 Y:2002 | 05 | 2002 | INSULATE BARE EQUIPMENT | $6,444 | $6,536 | Not Implemented |
NC0229 # 06 Y:2002 | 06 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $2,372 | $2,996 | Implemented |
NC0229 # 07 Y:2002 | 07 | 2002 | USE OPTIMUM THICKNESS INSULATION | $298 | $860 | Not Implemented |
NC0229 # 08 Y:2002 | 08 | 2002 | USE PHOTOCELL CONTROLS | $260 | $300 | Implemented |
NC0230 # 01 Y:2002 | 01 | 2002 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $22,396 | $5,000 | Not Implemented |
NC0230 # 02 Y:2002 | 02 | 2002 | DEVELOP A REPAIR/REPLACE POLICY | $1,099 | $1,354 | Implemented |