IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

540

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NL0051 # 04 Y:2020 04 2020 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,333 $13,737 Not Implemented
NL0051 # 05 Y:2020 05 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $631 $500 Implemented
NL0051 # 06 Y:2020 06 2020 ELIMINATE LEAKS IN WATER LINES AND VALVES $435 $85 Implemented
NL0051 # 07 Y:2020 07 2020 INSTALL OCCUPANCY SENSORS $418 $1,250 Not Implemented
NL0049 # 01 Y:2020 01 2020 OPTIMIZE PLANT POWER FACTOR $27,083 $43,749 Not Implemented
NL0049 # 02 Y:2020 02 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $19,291 $28,235 Implemented
NL0049 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,662 $4,000 Not Implemented
NL0049 # 04 Y:2020 04 2020 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $3,390 $90 Not Implemented
NL0049 # 05 Y:2020 05 2020 INSTALL SUB-METERING EQUIPMENT $2,954 $354 Implemented
NL0049 # 06 Y:2020 06 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,894 $2,550 Not Implemented
NL0049 # 07 Y:2020 07 2020 INSULATE BARE EQUIPMENT $1,475 $460 Not Implemented
NL0050 # 01 Y:2020 01 2020 USE AUTOMATIC CLEANING EQUIPMENT $4,536 $22,386 Implemented
NL0050 # 02 Y:2020 02 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,749 $5,975 Implemented
NL0050 # 03 Y:2020 03 2020 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $328 $2,465 Implemented
NL0050 # 04 Y:2020 04 2020 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $117 $388 Implemented
NL0050 # 05 Y:2020 05 2020 INSULATE BARE EQUIPMENT $58 $280 Implemented
NL0048 # 01 Y:2020 01 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $71,559 $111,731 Implemented
NL0048 # 02 Y:2020 02 2020 OPTIMIZE PLANT POWER FACTOR $24,509 $66,100 Not Implemented
NL0048 # 03 Y:2020 03 2020 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $22,004 $20,500 Not Implemented
NL0048 # 04 Y:2020 04 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,955 $4,000 Implemented
NL0048 # 05 Y:2020 05 2020 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,824 $50 Implemented
NL0048 # 06 Y:2020 06 2020 RECOVER AND REUSE WASTE MATERIAL $664 $3,180 Not Implemented
NL0047 # 01 Y:2020 01 2020 MINIMIZE WATER USAGE $75,018 $1,383 Not Implemented
NL0047 # 02 Y:2020 02 2020 METER WASTE WATER $41,210 $15,000 Implemented
NL0047 # 03 Y:2020 03 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,600 $6,024 Implemented