Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,795
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1004 # 01 Y:2019 | 01 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,732 | $6,990 | Not Implemented |
OK1004 # 02 Y:2019 | 02 | 2019 | IMPROVE COMBUSTION CONTROL CAPABILITY | $5,516 | $18,500 | Not Implemented |
OK1004 # 03 Y:2019 | 03 | 2019 | INSTALL OCCUPANCY SENSORS | $255 | $1,132 | Not Implemented |
OK1004 # 04 Y:2019 | 04 | 2019 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $679 | $1,295 | Not Implemented |
OK1004 # 05 Y:2019 | 05 | 2019 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,751 | $8,520 | Not Implemented |
OK1003 # 01 Y:2019 | 01 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,820 | $1,545 | Implemented |
OK1003 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,094 | $11,817 | Implemented |
OK1003 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,476 | $56,018 | Implemented |
OK1003 # 04 Y:2019 | 04 | 2019 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,431 | $7,700 | Not Implemented |
OK1003 # 05 Y:2019 | 05 | 2019 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $10,817 | $1,400 | Implemented |
OK1003 # 06 Y:2019 | 06 | 2019 | PAY UTILITY BILLS ON TIME | $9,631 | $0 | Not Implemented |
OK1003 # 07 Y:2019 | 07 | 2019 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $48,286 | $9,545 | Implemented |
OK1003 # 08 Y:2019 | 08 | 2019 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,867 | $4,544 | Not Implemented |
OK1002 # 01 Y:2019 | 01 | 2019 | OPTIMIZE PLANT POWER FACTOR | $20,293 | $28,306 | Not Implemented |
OK1002 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,343 | $2,609 | Implemented |
OK1002 # 03 Y:2019 | 03 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,400 | $2,933 | Implemented |
OK1002 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,768 | $3,646 | Implemented |
OK1002 # 05 Y:2019 | 05 | 2019 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $191,600 | $806,420 | Not Implemented |
OK1002 # 06 Y:2019 | 06 | 2019 | INSTALL SET-BACK TIMERS | $1,083 | $802 | Implemented |
OK1002 # 07 Y:2019 | 07 | 2019 | USE RADIANT HEATER FOR SPOT HEATING | $39,703 | $37,000 | Not Implemented |
OK1001 # 01 Y:2019 | 01 | 2019 | OPTIMIZE PLANT POWER FACTOR | $1,894 | $955 | Not Implemented |
OK1001 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,799 | $3,509 | Implemented |
OK1001 # 03 Y:2019 | 03 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,474 | $11,240 | Not Implemented |
OK1001 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,178 | $16,224 | Not Implemented |
OK1001 # 05 Y:2019 | 05 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,655 | $15,329 | Not Implemented |