Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
192
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0562 # 07 Y:1998 | 07 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $7,200 | $288 | Implemented |
OK0562 # 01 Y:1998 | 01 | 1998 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $14,801 | $1,936 | Implemented |
OK0562 # 09 Y:1998 | 09 | 1998 | METER WASTE WATER | $233 | $0 | Implemented |
OK0562 # 08 Y:1998 | 08 | 1998 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $2,160 | $0 | Implemented |
OK0562 # 05 Y:1998 | 05 | 1998 | INSTALL OCCUPANCY SENSORS | $360 | $532 | Implemented |
OK0562 # 02 Y:1998 | 02 | 1998 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,344 | $1,516 | Not Implemented |
OK0562 # 04 Y:1998 | 04 | 1998 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $526 | $242 | Not Implemented |
OK0562 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $850 | $110 | Implemented |
OK0562 # 06 Y:1998 | 06 | 1998 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $7,243 | $0 | Not Implemented |
OK0540 # 04 Y:1998 | 04 | 1998 | INSTALL OCCUPANCY SENSORS | $783 | $1,188 | n/a |
OK0540 # 03 Y:1998 | 03 | 1998 | OPTIMIZE PLANT POWER FACTOR | $2,129 | $0 | n/a |
OK0540 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,180 | $2,828 | n/a |
OK0540 # 01 Y:1998 | 01 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $5,006 | $9,000 | n/a |
OK0540 # 05 Y:1998 | 05 | 1998 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $1,226 | $5,610 | n/a |
OK0540 # 06 Y:1998 | 06 | 1998 | MOVE PRODUCT USING MECHANICAL MEANS | $6,531 | $0 | n/a |
OK0561 # 04 Y:1998 | 04 | 1998 | INSTALL OCCUPANCY SENSORS | $640 | $3,078 | Not Implemented |
OK0561 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $588 | $1,039 | Implemented |
OK0561 # 06 Y:1998 | 06 | 1998 | IMPROVE SPACE COMFORT CONDITIONING | $15,475 | $1,800 | Implemented |
OK0561 # 07 Y:1998 | 07 | 1998 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $5,369 | $0 | Implemented |
OK0561 # 05 Y:1998 | 05 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,911 | $0 | Not Implemented |
OK0561 # 03 Y:1998 | 03 | 1998 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $629 | $340 | Not Implemented |
OK0561 # 01 Y:1998 | 01 | 1998 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $2,306 | $5,000 | Implemented |
OK0560 # 04 Y:1998 | 04 | 1998 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $6,750 | $59,000 | Not Implemented |
OK0560 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $329 | $1,158 | Implemented |
OK0560 # 03 Y:1998 | 03 | 1998 | IMPROVE SPACE COMFORT CONDITIONING | $84,000 | $330,000 | Implemented |